6331 W 83RD ST 90045
Certificate Information: 6331 W 83RD ST 90045
- Application / Permit
- 22016-10000-15514
- Plan Check / Job No.
- B22LA09662
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING GARAGE INTO ACCESSORY DWELLING UNIT
- Permit Issued
- Issued on 6/23/2022
- Issuing Office
- Current Status
- CofO Issued on 2/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/20/2022 | GEORGE ALVAREZ |
| Corrections Issued | 5/20/2022 | GEORGE ALVAREZ |
| Plan Check Approved | 6/1/2022 | FERNANDO FLORES |
| Issued | 6/23/2022 | APPLICANT |
| Building Plans Picked Up | 6/29/2022 | APPLICANT |
| CofO in Progress | 2/1/2023 | HERBERT GIRON |
| Permit Finaled | 2/7/2023 | DANIEL ORRANTE |
| CofO Issued | 2/7/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/7/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 5/25/2022 | FREDDY GARCIA |
| Address approval | Cleared | 5/26/2022 | CATHERINE ADROVER |
| Eng Process Fee Ord 176,300 | Cleared | 5/26/2022 | CATHERINE ADROVER |
| Sewer availability | Cleared | 5/26/2022 | CATHERINE ADROVER |
Contact Information
| Contractor | A R M Builders Inc; Lic. No.: 915352-B | 1080 S LA CIENEGA #311 LOS ANGELES, CA 90035 |
| Contractor | Owner-Builder | , |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/29/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Deputy Drilled-In Anchors | 6/30/2022 | Conditional Approval | RICHARD STEINBACH |
| Footing/Foundation/Slab | 7/1/2022 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 7/19/2022 | Not Ready for Inspection | HERBERT GIRON |
| Wood Frame | 7/19/2022 | Conditional Approval | HERBERT GIRON |
| Insulation | 7/28/2022 | Conditional Approval | HERBERT GIRON |
| ELECTRICAL-Rough | 8/10/2022 | Corrections Issued | HERBERT GIRON |
| HVAC-Rough | 8/10/2022 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 8/10/2022 | Corrections Issued | HERBERT GIRON |
| BUILDING-Rough-Frame | 8/12/2022 | Not Ready for Inspection | HERBERT GIRON |
| ELECTRICAL-Rough | 8/12/2022 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2022 | Partial Approval | HERBERT GIRON |
| HVAC-Rough | 8/12/2022 | Approved | HERBERT GIRON |
| PLUMBING-Rough | 8/12/2022 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 9/1/2022 | Not Ready for Inspection | HERBERT GIRON |
| Insulation | 9/1/2022 | Corrections Issued | HERBERT GIRON |
| Interior/Exterior Lathing | 9/1/2022 | Partial Approval | HERBERT GIRON |
| Wood Frame | 9/1/2022 | Not Ready for Inspection | HERBERT GIRON |
| BUILDING-Rough-Frame | 9/8/2022 | Approved | HERBERT GIRON |
| Insulation | 9/8/2022 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 9/12/2022 | Corrections Issued | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2022 | Not Ready for Inspection | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/3/2022 | Approved | HERBERT GIRON |
| Drywall Nailing | 10/12/2022 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 11/14/2022 | Not Ready for Inspection | HERBERT GIRON |
| Shower Pan | 11/14/2022 | Corrections Issued | HERBERT GIRON |
| Interior/Exterior Lathing | 11/18/2022 | Partial Approval | CLAYTON GRAHAM |
| Shower Pan | 11/18/2022 | Corrections Issued | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 11/23/2022 | Approved | HERBERT GIRON |
| Shower Pan | 11/23/2022 | Approved | HERBERT GIRON |
| Sewer | 12/19/2022 | Approved | HERBERT GIRON |
| Underground Mechanical | 12/19/2022 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 12/22/2022 | SGSOV Not Ready | HERBERT GIRON |
| ELECTRICAL-Final | 12/27/2022 | Corrections Issued | EVAN COOPER |
| Final | 12/27/2022 | Corrections Issued | EVAN COOPER |
| HVAC-Final | 12/27/2022 | Corrections Issued | EVAN COOPER |
| PLUMBING-Final | 12/27/2022 | Corrections Issued | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 12/27/2022 | SGSOV Not Ready | EVAN COOPER |
| Smoke Detectors | 12/27/2022 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 1/24/2023 | Corrections Issued | HERBERT GIRON |
| Final | 1/24/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 1/24/2023 | Approved | HERBERT GIRON |
| PLUMBING-Final | 1/24/2023 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 1/31/2023 | Approved | HERBERT GIRON |
| Final | 1/31/2023 | OK to Issue CofO | HERBERT GIRON |
| Gas Test | 1/31/2023 | Approved | HERBERT GIRON |
| PLUMBING-Final | 1/31/2023 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 1/31/2023 | SGSOV Approved | HERBERT GIRON |