11127 S BELHAVEN ST 90059

Certificate Information: 11127 S BELHAVEN ST 90059

Application / Permit
22016-10000-15409
Plan Check / Job No.
B22LA09591
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan: Covert Garage into ADU PER GCS65852.2(e)(1)(A
Permit Issued
Issued on 7/8/2022
Issuing Office
Current Status
CofO Issued on 1/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/24/2022 APPLICANT
Assigned to Plan Check Engineer 5/25/2022 RICARDO RAMIREZ
Corrections Issued 5/26/2022 RICARDO RAMIREZ
Plan Check Approved 6/30/2022 RICARDO RAMIREZ
Issued 7/8/2022 APPLICANT
CofO in Progress 1/6/2024 JOHN KLARIN
Permit Finaled 1/16/2024 ANSON MAGLASANG
CofO Issued 1/16/2024 ANSON MAGLASANG
Permit Finaled 1/16/2024 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 6/16/2022 CINDY QI
Sewer availability Cleared 6/16/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 6/21/2022 CINDY QI

Contact Information

Contractor Owner-Builder       ,
Engineer Herrera,, Edgar E; Lic. No.: NA67603       ,

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/3/2022 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 1/18/2023 Partial Approval JOHN KLARIN
ELECTRICAL-Rough 1/18/2023 Approved JOHN KLARIN
PLUMBING-Rough 1/18/2023 Approved JOHN KLARIN
Sewer 1/18/2023 Approved JOHN KLARIN
Wood Frame 1/18/2023 Partial Approval JOHN KLARIN
Insulation 2/1/2023 Approved JOHN KLARIN
Drywall Nailing 2/7/2023 Approved JAMES CHAVEZ
BUILDING-Rough-Frame 7/19/2023 Approved JOHN KLARIN
ELECTRICAL-Final 7/19/2023 Corrections Issued JOHN KLARIN
Final 7/19/2023 Corrections Issued JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 7/19/2023 SGSOV Approved JOHN KLARIN
Smoke Detectors 7/19/2023 Corrections Issued JOHN KLARIN
ELECTRICAL-Final 9/6/2023 Corrections Issued JOHN KLARIN
Final 9/6/2023 Corrections Issued JOHN KLARIN
PLUMBING-Final 9/6/2023 Corrections Issued JOHN KLARIN
Service/Power Release 9/6/2023 Not Ready for Inspection JOHN KLARIN
Smoke Detectors 9/6/2023 Corrections Issued JOHN KLARIN
ELECTRICAL-Final 10/12/2023 Approved JOHN KLARIN
Final 10/12/2023 Corrections Issued JOHN KLARIN
Service/Power Release 10/12/2023 Not Ready for Inspection JOHN KLARIN
Smoke Detectors 10/12/2023 Approved JOHN KLARIN
Final 10/19/2023 Not Ready for Inspection JOHN KLARIN
Final 10/31/2023 Corrections Issued JAMES CHAVEZ
Final 12/7/2023 Not Ready for Inspection JOHN KLARIN
ELECTRICAL-Final 1/5/2024 Approved JOHN KLARIN
Final 1/5/2024 OK to Issue CofO JOHN KLARIN
HVAC-Final 1/5/2024 Approved JOHN KLARIN
PLUMBING-Final 1/5/2024 Approved JOHN KLARIN
Service/Power Release 1/5/2024 Approved JOHN KLARIN
Wood Frame 1/5/2024 Approved JOHN KLARIN