11127 S BELHAVEN ST 90059
Certificate Information: 11127 S BELHAVEN ST 90059
- Application / Permit
- 22016-10000-15409
- Plan Check / Job No.
- B22LA09591
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: Covert Garage into ADU PER GCS65852.2(e)(1)(A
- Permit Issued
- Issued on 7/8/2022
- Issuing Office
- Current Status
- CofO Issued on 1/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/24/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/25/2022 | RICARDO RAMIREZ |
| Corrections Issued | 5/26/2022 | RICARDO RAMIREZ |
| Plan Check Approved | 6/30/2022 | RICARDO RAMIREZ |
| Issued | 7/8/2022 | APPLICANT |
| CofO in Progress | 1/6/2024 | JOHN KLARIN |
| Permit Finaled | 1/16/2024 | ANSON MAGLASANG |
| CofO Issued | 1/16/2024 | ANSON MAGLASANG |
| Permit Finaled | 1/16/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 6/16/2022 | CINDY QI |
| Sewer availability | Cleared | 6/16/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 6/21/2022 | CINDY QI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Herrera,, Edgar E; Lic. No.: NA67603 | , |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/3/2022 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 1/18/2023 | Partial Approval | JOHN KLARIN |
| ELECTRICAL-Rough | 1/18/2023 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 1/18/2023 | Approved | JOHN KLARIN |
| Sewer | 1/18/2023 | Approved | JOHN KLARIN |
| Wood Frame | 1/18/2023 | Partial Approval | JOHN KLARIN |
| Insulation | 2/1/2023 | Approved | JOHN KLARIN |
| Drywall Nailing | 2/7/2023 | Approved | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 7/19/2023 | Approved | JOHN KLARIN |
| ELECTRICAL-Final | 7/19/2023 | Corrections Issued | JOHN KLARIN |
| Final | 7/19/2023 | Corrections Issued | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 7/19/2023 | SGSOV Approved | JOHN KLARIN |
| Smoke Detectors | 7/19/2023 | Corrections Issued | JOHN KLARIN |
| ELECTRICAL-Final | 9/6/2023 | Corrections Issued | JOHN KLARIN |
| Final | 9/6/2023 | Corrections Issued | JOHN KLARIN |
| PLUMBING-Final | 9/6/2023 | Corrections Issued | JOHN KLARIN |
| Service/Power Release | 9/6/2023 | Not Ready for Inspection | JOHN KLARIN |
| Smoke Detectors | 9/6/2023 | Corrections Issued | JOHN KLARIN |
| ELECTRICAL-Final | 10/12/2023 | Approved | JOHN KLARIN |
| Final | 10/12/2023 | Corrections Issued | JOHN KLARIN |
| Service/Power Release | 10/12/2023 | Not Ready for Inspection | JOHN KLARIN |
| Smoke Detectors | 10/12/2023 | Approved | JOHN KLARIN |
| Final | 10/19/2023 | Not Ready for Inspection | JOHN KLARIN |
| Final | 10/31/2023 | Corrections Issued | JAMES CHAVEZ |
| Final | 12/7/2023 | Not Ready for Inspection | JOHN KLARIN |
| ELECTRICAL-Final | 1/5/2024 | Approved | JOHN KLARIN |
| Final | 1/5/2024 | OK to Issue CofO | JOHN KLARIN |
| HVAC-Final | 1/5/2024 | Approved | JOHN KLARIN |
| PLUMBING-Final | 1/5/2024 | Approved | JOHN KLARIN |
| Service/Power Release | 1/5/2024 | Approved | JOHN KLARIN |
| Wood Frame | 1/5/2024 | Approved | JOHN KLARIN |