3101 S BARRY AVE 90066
Certificate Information: 3101 S BARRY AVE 90066
- Application / Permit
- 22016-10000-15348
- Plan Check / Job No.
- B22LA09545
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- KITCHEN REMODEL INCLUDING VAULTED CEILING, NEW WINDOWS THROUGHOUT KITCHEN AREA IN EXISTING ONE STORY SINGLE FAMILY DEWLLING
- Permit Issued
- Issued on 7/19/2022
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 1/12/2023
Permit Application Status History
| Submitted | 5/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/19/2022 | CRISTINA SALAZAR |
| Corrections Issued | 5/19/2022 | CRISTINA SALAZAR |
| Plan Check Approved | 7/11/2022 | AUNG SOE |
| Issued | 7/19/2022 | APPLICANT |
| Permit Finaled | 1/11/2023 | JOHNNY MIRANDA |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 7/6/2022 | KIRK LINKLATER |
Contact Information
| Contractor | E H D Builders Inc; Lic. No.: 1034101-B | 18375 VENTURA BLVD 122 TARZANA, CA 91356 |
| Engineer | Sin,, John Paul; Lic. No.: C91162 | 122 N GRAMERCY PL LOS ANGELES, CA 90004 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/8/2022 | Conditional Approval | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 11/9/2022 | Partial Approval | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 11/9/2022 | Approved | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 11/9/2022 | Corrections Issued | JOHNNY MIRANDA |
| HVAC-Rough | 11/9/2022 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 11/9/2022 | Approved | JOHNNY MIRANDA |
| PLUMBING-Rough | 11/9/2022 | Approved | JOHNNY MIRANDA |
| Wood Frame | 11/9/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 11/16/2022 | Partial Approval | JOHNNY MIRANDA |
| Insulation | 11/16/2022 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 11/21/2022 | Approved | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2022 | Approved | JOHNNY MIRANDA |
| Deputy Wood Construction | 11/22/2022 | Conditional Approval | MICHAEL PELHAM |
| Drywall Nailing | 11/28/2022 | Approved | DAVID FEILER |
| Final | 1/11/2023 | Permit Finaled | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 1/11/2023 | SGSOV Approved | JOHNNY MIRANDA |
| Smoke Detectors | 1/11/2023 | Approved | JOHNNY MIRANDA |