2212-2214 N GLENDALE BLVD 90039
Certificate Information: 2212-2214 N GLENDALE BLVD 90039
- Application / Permit
- 22016-10000-15060
- Plan Check / Job No.
- B22LA09353
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT EXISITING 419 SF STORAGE INTO A NEW ADU IN EXISTING 2 STORY SINGLE FAMILY DEWLLING (Attached ADU per Ordinance, LAMC 12.22 A.33(c) and (e))
- Permit Issued
- Issued on 11/3/2022
- Issuing Office
- Current Status
- CofO Issued on 9/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/20/2022 | ZAW HAN |
| Corrections Issued | 5/24/2022 | ZAW HAN |
| Applicant returned to address corrections | 7/22/2022 | ZAW HAN |
| Plan Check Approved | 9/8/2022 | AUNG SOE |
| Issued | 11/3/2022 | APPLICANT |
| Building Plans Picked Up | 11/23/2022 | APPLICANT |
| CofO in Progress | 9/24/2025 | HAMIK HARTOUNIAN |
| Permit Finaled | 9/26/2025 | DEROLD HAUFF |
| CofO Issued | 9/26/2025 | DEROLD HAUFF |
| Permit Finaled | 9/26/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/10/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 6/10/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 6/28/2022 | JEANETTE VONG |
Contact Information
| Contractor | Regreen Inc; Lic. No.: 939440-B | 17101 S CENTRAL AVENUE UNIT 1K CARSON, CA 90746 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/15/2022 | Corrections Issued | THOMAS LOGRASSO |
| Pre-Inspection | 8/30/2023 | Partial Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 7/16/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 7/16/2024 | Partial Approval | HAMIK HARTOUNIAN |
| Green Building Rough | 7/16/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| HVAC-Rough | 7/16/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| MERV13>=Rough | 7/16/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 7/16/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| HVAC-Rough | 7/18/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 7/18/2024 | Partial Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 7/22/2024 | Corrections Issued | SCOTT FINNILA |
| Green Building Rough | 7/22/2024 | Partial Inspection | SCOTT FINNILA |
| HVAC-Rough | 7/22/2024 | Partial Inspection | SCOTT FINNILA |
| MERV13>=Rough | 7/22/2024 | Partial Inspection | SCOTT FINNILA |
| BUILDING-Rough-Frame | 7/26/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Green Building Rough | 7/26/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| HVAC-Rough | 7/26/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| MERV13>=Rough | 7/26/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 7/30/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Wood Frame | 7/30/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 8/7/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Rough | 8/7/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| HVAC-Rough | 8/7/2024 | Partial Approval | HAMIK HARTOUNIAN |
| MERV13>=Rough | 8/7/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 8/8/2024 | Partial Approval | FREDDIE RIVERA |
| Green Building Rough | 8/8/2024 | Approved | FREDDIE RIVERA |
| Insulation | 8/8/2024 | Approved | FREDDIE RIVERA |
| MERV13>=Rough | 8/8/2024 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 8/12/2024 | Partial Approval | FREDDIE RIVERA |
| Interior/Exterior Lathing | 8/12/2024 | Partial Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 10/1/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 10/1/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 10/1/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| MERV13>=Final | 10/1/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 10/1/2024 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Smoke Detectors | 10/1/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 10/10/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Final | 10/10/2024 | Partial Inspection | HAMIK HARTOUNIAN |
| Green Building Final | 10/10/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| MERV13>=Final | 10/10/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 10/10/2024 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Smoke Detectors | 10/10/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Pre-Inspection | 11/20/2024 | Not Ready for Inspection | LUIS CASTRO |
| Footing/Foundation/Slab | 4/8/2025 | Conditional Approval | HAMIK HARTOUNIAN |
| Underground Mechanical | 4/8/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 4/14/2025 | Partial Approval | LILIANA PORTILLO |
| ELECTRICAL-Rough | 5/8/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 5/8/2025 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 5/29/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Deputy Drilled-In Anchors | 5/29/2025 | Conditional Approval | OSVALDO PARAMO |
| Insulation | 5/29/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 6/4/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2025 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 6/16/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 6/16/2025 | Partial Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 6/18/2025 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 6/18/2025 | Approved | HAMIK HARTOUNIAN |
| Insulation | 6/25/2025 | Approved | ALEX COLIN |
| BUILDING-Rough-Frame | 6/26/2025 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 7/1/2025 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 7/1/2025 | Approved | ALEX COLIN |
| Special/Order Compliance | 7/1/2025 | Partial Inspection | DEVON JACKSON |
| ELECTRICAL-Final | 9/8/2025 | Approved | HAMIK HARTOUNIAN |
| Final | 9/8/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 9/8/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| HVAC-Final | 9/8/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| MERV13>=Final | 9/8/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Final | 9/8/2025 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 9/8/2025 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 9/8/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 9/12/2025 | Corrections Issued | JOSE MACIAS |
| Green Building Final | 9/12/2025 | Approved | JOSE MACIAS |
| MERV13>=Final | 9/12/2025 | Approved | JOSE MACIAS |
| Smoke Detectors | 9/12/2025 | Approved | JOSE MACIAS |
| Final | 9/17/2025 | Partial Inspection | HAMIK HARTOUNIAN |
| Final | 9/19/2025 | Partial Inspection | HAMIK HARTOUNIAN |
| Final | 9/24/2025 | OK to Issue CofO | HAMIK HARTOUNIAN |