1542 S HI POINT ST 90035

Certificate Information: 1542 S HI POINT ST 90035

Application / Permit
22016-10000-15019
Plan Check / Job No.
B22LA09319
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Eplan: Soft-Story seismic retrofit per LABC Chapter 93: USING (1) SPECIAL CANTILEVERED COLUMN (2 WAY) W/ GRADE BEAMS AND (4) WOOD SHEAR WALLS.
Permit Issued
Issued on 7/28/2022
Issuing Office
Current Status
CofC Issued on 12/27/2022

Permit Application Status History

Submitted 5/17/2022 APPLICANT
Assigned to Plan Check Engineer 5/26/2022 VARAND SARKISIAN
Corrections Issued 6/1/2022 VARAND SARKISIAN
Quality Review Completed 6/7/2022 HANS SANTIAGO
Plan Check Approved 6/29/2022 VARAND SARKISIAN
Issued 7/28/2022 APPLICANT
OK for CofC 12/9/2022 DARRYL ARNOLD
CofC Issued 12/27/2022 WINSTON DUNNING

Permit Application Clearance Information

Tenant Habitability Plan Cleared 7/27/2022 ISMAEL HERNANDEZ

Contact Information

Contractor Zebra Construction Inc; Lic. No.: 1055609-B 2523 S ROBERTSON BLVD      LOS ANGELES, CA 90034
Engineer Ni,, Zhang Yuan; Lic. No.: C68149 8232 GARVEY AVE 203      ROSEMEAD, CA 91770

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/30/2022 Conditional Approval DARRYL ARNOLD
Deputy Drilled-In Anchors 9/19/2022 Conditional Approval DARRYL ARNOLD
Footing/Foundation/Slab 9/21/2022 Approved DARRYL ARNOLD
Structural Steel Frame 9/21/2022 Approved DARRYL ARNOLD
Wood Frame 9/21/2022 Approved DARRYL ARNOLD
Interior/Exterior Lathing 10/3/2022 Not Ready for Inspection BRUCE CAMPBELL
Interior/Exterior Lathing 10/4/2022 Corrections Issued BRUCE CAMPBELL
Interior/Exterior Lathing 10/11/2022 Conditional Approval DARRYL ARNOLD
Final 10/24/2022 Not Ready for Inspection DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 10/24/2022 SGSOV Not Ready DARRYL ARNOLD
Smoke Detectors 10/24/2022 Approved DARRYL ARNOLD
Final 11/9/2022 Conditional Approval DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 11/9/2022 SGSOV Approved DARRYL ARNOLD
Final 12/9/2022 OK for CofC DARRYL ARNOLD