11100 W PEORIA ST 91352

Certificate Information: 11100 W PEORIA ST 91352

Application / Permit
22016-10000-15011
Plan Check / Job No.
B22LA09309
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(21) Motion Picture Studio
Work Description
DEFERRED SUBMITTAL : INSTALL 7 EXTERIOR ELEPHANT DOORS FOR BP2 & BP3 (BUILDING 1 , PERMIT APPLICATION # 21010-10000-01829)
Permit Issued
Issued on 9/21/2022
Issuing Office
Metro
Current Status
Permit Finaled on 9/11/2024

Permit Application Status History

Submitted 5/17/2022 APPLICANT
Assigned to Plan Check Engineer 6/16/2022 GARO TELMI
Disabled Access Plans Picked Up 7/14/2022 APPLICANT
Corrections Issued 7/27/2022 GARO TELMI
Quality Review Completed 7/29/2022 KEN GILL
Building Plans Picked Up 7/29/2022 APPLICANT
Applicant returned to address corrections 9/8/2022 GARO TELMI
Plan Check Approved 9/21/2022 GARO TELMI
Issued 9/21/2022 APPLICANT
Permit Finaled 9/11/2024 DANNY RODRIGUEZ

Permit Application Clearance Information

DAS Clearance Cleared 9/20/2022 EDDIE GARIN

Contact Information

Architect Bastien,, Gary L; Lic. No.: C11164 15661 RED HILL AVENUE SUITE 150      TUSTIN, CA 92780
Contractor Snyder Langston Llc; Lic. No.: 1019188-B 17962 COWAN      IRVINE, CA 92614
Engineer Haas,, Kyle; Lic. No.: S6494 564A LOMBARD STREET      SAN FRANCISCO, CA 94133

Inspector Information

JOHN KITCKO, (818) 374-1109 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Reinforced Concrete Frame 5/5/2023 Not Ready for Inspection ANDREW DORSO
Reinforced Concrete Frame 5/8/2023 Partial Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 5/9/2023 Partial Approval DANNY RODRIGUEZ
Final 3/8/2024 Partial Inspection DANNY RODRIGUEZ
Green Building Final 3/8/2024 Not Ready for Inspection DANNY RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 3/8/2024 SGSOV Not Ready DANNY RODRIGUEZ
Smoke Detectors 3/8/2024 Not Ready for Inspection DANNY RODRIGUEZ