1617 S CRESCENT HEIGHTS BLVD 90035

Certificate Information: 1617 S CRESCENT HEIGHTS BLVD 90035

Application / Permit
22016-10000-14899
Plan Check / Job No.
B22LA09284
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 1/24/2023
Issuing Office
Metro
Current Status
CofO Issued on 4/8/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/16/2022 APPLICANT
Assigned to Plan Check Engineer 5/16/2022 SHANGQIN XIE
Corrections Issued 5/16/2022 SHANGQIN XIE
Plan Check Approved 7/28/2022 GEORGE ALVAREZ
Issued 1/24/2023 APPLICANT
CofO in Progress 3/29/2024 STUART CHAPMAN
Permit Finaled 4/8/2024 DEROLD HAUFF
CofO Issued 4/8/2024 DEROLD HAUFF
Permit Finaled 4/8/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/19/2022 STEVE MELGAR
Sewer availability Cleared 5/19/2022 STEVE MELGAR
Construction within easement Cleared 7/20/2022 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 7/27/2022 AMY SHUM

Contact Information

Contractor Owner-Builder       ,
Engineer Yu,, Kunyoung; Lic. No.: C66880 22812 ERIEL AVE      TORRANCE, CA 90505

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/8/2023 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 8/31/2023 Corrections Issued JOSE AVILA
Deputy Drilled-In Anchors 9/21/2023 Conditional Approval JOSE AVILA
Footing/Foundation/Slab 9/21/2023 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 9/26/2023 Approved JOSE AVILA
Deputy Drilled-In Anchors 10/16/2023 Conditional Approval JOSE AVILA
Footing/Foundation/Slab 10/18/2023 Approved JOSE AVILA
ELECTRICAL-Rough 10/27/2023 Approved RONNIE MINDANAO
HVAC-Rough 10/27/2023 Not Ready for Inspection RONNIE MINDANAO
PLUMBING-Rough 10/27/2023 Corrections Issued RONNIE MINDANAO
METHANE-Rough 10/31/2023 Approved JOSE AVILA
Underground Mechanical 10/31/2023 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 11/7/2023 Partial Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 11/13/2023 Conditional Approval LILIANA PORTILLO
Insulation 11/13/2023 Corrections Issued LILIANA PORTILLO
Interior/Exterior Lathing 11/13/2023 Partial Approval LILIANA PORTILLO
HVAC-Rough 11/16/2023 Partial Approval RONNIE MINDANAO
PLUMBING-Rough 11/16/2023 Corrections Issued RONNIE MINDANAO
HVAC-Rough 11/21/2023 Corrections Issued JOAQUIN GREENOUGH
Insulation 11/21/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Interior/Exterior Lathing 11/21/2023 Not Ready for Inspection JOAQUIN GREENOUGH
PLUMBING-Rough 11/21/2023 Corrections Issued JOAQUIN GREENOUGH
BUILDING-Rough-Frame 11/29/2023 Corrections Issued JOSE AVILA
HVAC-Rough 11/29/2023 Approved JOSE AVILA
Interior/Exterior Lathing 11/29/2023 Approved JOSE AVILA
PLUMBING-Rough 11/29/2023 Approved JOSE AVILA
BUILDING-Rough-Frame 12/8/2023 Conditional Approval JOAQUIN GREENOUGH
Shower Pan 12/8/2023 Approved JOAQUIN GREENOUGH
Insulation 12/13/2023 Approved RONNIE MINDANAO
Drywall Nailing 1/9/2024 Corrections Issued RONNIE MINDANAO
BUILDING-Rough-Frame 3/1/2024 Approved JOSEPH MCGARRY
Drywall Nailing 3/1/2024 Approved JOSEPH MCGARRY
Final 3/1/2024 Corrections Issued JOSEPH MCGARRY
Gas Test 3/1/2024 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 3/1/2024 SGSOV Approved JOSEPH MCGARRY
Smoke Detectors 3/1/2024 Approved JOSEPH MCGARRY
Final 3/5/2024 Corrections Issued STUART CHAPMAN
ELECTRICAL-Final 3/11/2024 Approved STUART CHAPMAN
Final 3/11/2024 Conditional Approval STUART CHAPMAN
HVAC-Final 3/11/2024 Approved STUART CHAPMAN
PLUMBING-Final 3/11/2024 Approved STUART CHAPMAN
Final 3/29/2024 OK to Issue CofO STUART CHAPMAN
Service/Power Release 3/29/2024 Approved STUART CHAPMAN