1439-1441 W 37TH DR 90018
Certificate Information: 1439-1441 W 37TH DR 90018
- Application / Permit
- 22016-10000-14841
- Plan Check / Job No.
- B22LA09231
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- (E) Garage conversion to Accessory Dwelling Unit per CA Govt. Code 65852.2(e)(1)(C). All work per engineered plans. ADU Address: 1439 1/2 W 37th Dr.
- Permit Issued
- Issued on 8/7/2025
- Issuing Office
- Current Status
- Issued on 8/7/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/19/2022 | KHUONG TRUONG |
| Corrections Issued | 5/22/2022 | KHUONG TRUONG |
| Building Plans Picked Up | 5/25/2022 | APPLICANT |
| Plan Check Approved | 5/24/2023 | MICHAEL LANZONE |
| Issued | 8/7/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 5/31/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 6/13/2022 | CINDY QI |
| Sewer availability | Cleared | 6/13/2022 | CINDY QI |
Contact Information
| Contractor | Tripalink Builders Llc; Lic. No.: 1118224-B | 2905 S VERMONT AVE STE 203 LOS ANGELES, CA 90007 |
| Engineer | Tzeng,, Charles Chau-Jyi; Lic. No.: C34005 | PO BOX 5044 PASADENA, CA 91117 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| ELECTRICAL-Final | 7/24/2026 |
| PLUMBING-Final | 7/24/2026 |
| HVAC-Final | 7/24/2026 |
Inspection Request History
| Footing/Foundation/Slab | 10/20/2025 | Approved | SABAS ALONSO |
| Underground Mechanical | 10/20/2025 | Approved | SABAS ALONSO |
| Pre-Inspection | 11/20/2025 | Partial Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 12/10/2025 | Approved | SABAS ALONSO |
| HVAC-Rough | 12/10/2025 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 12/10/2025 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 2/6/2026 | Approved | SABAS ALONSO |
| Green Building Rough | 2/6/2026 | Approved | SABAS ALONSO |
| Verify Sprinkler Sign Off | 2/6/2026 | Approved | SABAS ALONSO |
| Insulation | 6/8/2026 | Approved | SABAS ALONSO |
| Drywall Nailing | 6/17/2026 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 7/2/2026 | Approved | SABAS ALONSO |