2311 S LONGWOOD AVE 90016
Certificate Information: 2311 S LONGWOOD AVE 90016
- Application / Permit
- 22016-10000-14732
- Plan Check / Job No.
- B22LA09123
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *EPLAN* CONVERT (E) DETACHED 2-CAR GARGAE TO ADU PER CA GC 65852.2(e)(1)(A). ALL PORTIONS OF GARAGE TO BE DEMO ONLY KEEPING 1' OF (E) WALL AND FOOTING. REBUILD ADU TO THE SAME DIM.
- Permit Issued
- Issued on 9/23/2022
- Issuing Office
- Current Status
- CofO Issued on 5/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/24/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/25/2022 | VIVIAN LAO |
| Corrections Issued | 5/26/2022 | VIVIAN LAO |
| Plan Check Approved | 6/10/2022 | VIVIAN LAO |
| Issued | 9/23/2022 | APPLICANT |
| CofO in Progress | 4/11/2023 | CALEB MEISTER |
| Permit Finaled | 5/21/2023 | DEROLD HAUFF |
| CofO Issued | 5/21/2023 | DEROLD HAUFF |
| Permit Finaled | 5/21/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/2/2022 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 6/2/2022 | JEANIE LAM |
| Sewer availability | Cleared | 6/2/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 6/8/2022 | JEANIE LAM |
Contact Information
| Contractor | New Generation Home Improvements Inc; Lic. No.: 938552-B | 5805 WHITE OAK AVE #18431 ENCINO, CA 91416 |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/24/2022 | Partial Approval | STUART CHAPMAN |
| Sewer | 10/24/2022 | Partial Approval | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 11/1/2022 | Approved | STUART CHAPMAN |
| Footing/Foundation/Slab | 11/1/2022 | Approved | STUART CHAPMAN |
| Sewer | 11/1/2022 | Approved | STUART CHAPMAN |
| Underground Mechanical | 11/1/2022 | Approved | STUART CHAPMAN |
| ELECTRICAL-Rough | 12/16/2022 | Not Ready for Inspection | CALEB MEISTER |
| HVAC-Rough | 12/16/2022 | Not Ready for Inspection | CALEB MEISTER |
| PLUMBING-Rough | 12/16/2022 | Not Ready for Inspection | CALEB MEISTER |
| Wood Frame | 12/16/2022 | Not Ready for Inspection | CALEB MEISTER |
| ELECTRICAL-Rough | 12/21/2022 | Approved | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 12/21/2022 | Approved | CALEB MEISTER |
| Green Building Rough | 12/21/2022 | Approved | CALEB MEISTER |
| HVAC-Rough | 12/21/2022 | Approved | CALEB MEISTER |
| MERV13>=Rough | 12/21/2022 | Approved | CALEB MEISTER |
| PLUMBING-Rough | 12/21/2022 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 1/12/2023 | Approved | MICHAEL LEWIS |
| Shower Pan | 1/12/2023 | Approved | MICHAEL LEWIS |
| Insulation | 1/13/2023 | Corrections Issued | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 1/20/2023 | Approved | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2023 | Approved | CALEB MEISTER |
| Insulation | 1/20/2023 | Approved | CALEB MEISTER |
| Drywall Nailing | 1/27/2023 | Approved | CALEB MEISTER |
| Final | 3/31/2023 | Corrections Issued | CALEB MEISTER |
| Green Building Final | 3/31/2023 | Approved | CALEB MEISTER |
| MERV13>=Final | 3/31/2023 | Approved | CALEB MEISTER |
| SGSOV-Seismic Gas S/O Valve | 3/31/2023 | SGSOV Approved | CALEB MEISTER |
| Smoke Detectors | 3/31/2023 | Approved | CALEB MEISTER |
| ELECTRICAL-Final | 4/10/2023 | Approved | CALEB MEISTER |
| Final | 4/10/2023 | OK to Issue CofO | CALEB MEISTER |
| HVAC-Final | 4/10/2023 | Approved | CALEB MEISTER |
| PLUMBING-Final | 4/10/2023 | Approved | CALEB MEISTER |