5272 W VERONICA ST 90008

Certificate Information: 5272 W VERONICA ST 90008

Application / Permit
22016-10000-14551
Plan Check / Job No.
B22LA09016
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan - Interior/Exterior Remodel of (E) 2-Story SFD with Addition of 40 SF to (E) Balcony.
Permit Issued
Issued on 6/27/2022
Issuing Office
Current Status
Permit Finaled on 2/14/2023

Permit Application Status History

Submitted 5/12/2022 APPLICANT
Assigned to Plan Check Engineer 5/17/2022 MINA HABILI
Corrections Issued 5/18/2022 MINA HABILI
Applicant returned to address corrections 5/31/2022 MINA HABILI
Plan Check Approved 6/15/2022 MINA HABILI
Issued 6/27/2022 APPLICANT
Permit Finaled 2/14/2023 BRENDAN MORELLI

Permit Application Clearance Information

Grading Pre-Inspection Cleared 5/26/2022 VASIL MIHALEV

Contact Information

Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/11/2022 Approved ANTHONY EGSON
Footing/Foundation/Slab 7/11/2022 Approved ANTHONY EGSON
Sewer 9/2/2022 Approved ANTHONY EGSON
BUILDING-Rough-Frame 9/12/2022 Not Ready for Inspection ANTHONY EGSON
HVAC-Rough 9/12/2022 Corrections Issued ANTHONY EGSON
Rough-Elec/Plmb/HVAC 9/12/2022 Partial Approval ANTHONY EGSON
Rough-Elec/Plmb/HVAC 9/15/2022 Partial Approval ANTHONY EGSON
ELECTRICAL-Rough 9/28/2022 Approved ANTHONY EGSON
HVAC-Rough 9/28/2022 Not Ready for Inspection ANTHONY EGSON
Wood Frame 9/28/2022 Partial Approval ANTHONY EGSON
Deputy Wood Construction 10/3/2022 Approved ANTHONY EGSON
HVAC-Rough 10/4/2022 Approved ANTHONY EGSON
Shower Pan 10/4/2022 Not Ready for Inspection ANTHONY EGSON
Wood Frame 10/4/2022 Corrections Issued ANTHONY EGSON
Insulation 10/11/2022 Approved ANTHONY EGSON
Shower Pan 10/11/2022 Corrections Issued ANTHONY EGSON
Drywall Nailing 10/24/2022 Approved ANTHONY EGSON
Interior/Exterior Lathing 10/24/2022 Approved ANTHONY EGSON
Shower Pan 10/24/2022 Approved ANTHONY EGSON
Interior/Exterior Lathing 11/17/2022 Approved ANTHONY EGSON
Service/Power Release 11/17/2022 Approved ANTHONY EGSON
ELECTRICAL-Final 1/27/2023 Corrections Issued ANTHONY EGSON
Final 1/27/2023 Not Ready for Inspection ANTHONY EGSON
HVAC-Final 1/27/2023 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Final 1/27/2023 Corrections Issued ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 1/27/2023 SGSOV Not Ready ANTHONY EGSON
Smoke Detectors 1/27/2023 Approved ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 2/8/2023 SGSOV Not Ready STUART CHAPMAN
ELECTRICAL-Final 2/14/2023 Approved BRENDAN MORELLI
Final 2/14/2023 Permit Finaled BRENDAN MORELLI
HVAC-Final 2/14/2023 Approved BRENDAN MORELLI
PLUMBING-Final 2/14/2023 Approved BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 2/14/2023 SGSOV Approved BRENDAN MORELLI