1153 S CAMDEN DR 90035

Certificate Information: 1153 S CAMDEN DR 90035

Application / Permit
22016-10000-14531
Plan Check / Job No.
B22LA09008
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
REMODEL DETACHED GARAGE, REMOVE PORTION ADD BATHROOM. (1 OF 2)
Permit Issued
Issued on 12/22/2022
Issuing Office
Valley
Current Status
Issued on 12/22/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/12/2022 APPLICANT
Assigned to Plan Check Engineer 5/26/2022 TSE MING HUANG
Green Plans Picked Up 6/2/2022 APPLICANT
Corrections Issued 6/8/2022 TSE MING HUANG
Quality Review Completed 6/14/2022 EUGENE BARBEAU
Building Plans Picked Up 6/15/2022 APPLICANT
Applicant returned to address corrections 8/10/2022 TSE MING HUANG
Applicant returned to address corrections 9/1/2022 TSE MING HUANG
Plan Check Approved 9/21/2022 TSE MING HUANG
Issued 12/22/2022 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 9/21/2022 TSE MING HUANG

Contact Information

Contractor Roth Development Group; Lic. No.: 1006385-B 1670 FAIRMOUNT ROAD      WESTLAKE VILLAGE, CA 91362
Engineer Funk,, David Lyle; Lic. No.: S5421 319 MAIN STREET      EL SEGUNDO, CA 90245

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/20/2023 Partial Approval ARAM AVEDISIAN
Deputy Drilled-In Anchors 8/1/2023 Conditional Approval CLAYTON GRAHAM
Footing/Foundation/Slab 8/1/2023 Approved BRENDAN LOONEY
Underground Mechanical 8/1/2023 Partial Approval BRENDAN LOONEY
Footing/Foundation/Slab 8/3/2023 Not Ready for Inspection CHRISTOPHER WILSON
Deputy Reinf. Concrete 8/4/2023 Conditional Approval DAVID FEILER
Rough-Elec/Plmb/HVAC 4/22/2024 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Rough 6/6/2024 Corrections Issued SEAN HAUPT
HVAC-Rough 6/6/2024 Corrections Issued SEAN HAUPT
PLUMBING-Rough 6/6/2024 Approved SEAN HAUPT
Rough-Elec/Plmb/HVAC 6/6/2024 Not Ready for Inspection SEAN HAUPT
Sewer 6/6/2024 Partial Approval SEAN HAUPT
Underground Mechanical 6/6/2024 Approved SEAN HAUPT
ELECTRICAL-Rough 6/11/2024 Approved TEMISTOCLES CAAL
HVAC-Rough 6/11/2024 Approved TEMISTOCLES CAAL
Deputy Drilled-In Anchors 8/5/2024 Conditional Approval MICHAEL PELHAM
BUILDING-Rough-Frame 8/13/2024 No Access for Inspection ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 8/13/2024 Not Ready for Inspection ASHLEY THOMPSON
Green Building Rough 8/13/2024 No Access for Inspection ASHLEY THOMPSON
METHANE-Rough 8/13/2024 No Access for Inspection ASHLEY THOMPSON
Special/Order Compliance 8/13/2024 Partial Inspection REGINA MENDEZ
Wood Frame 8/13/2024 Not Ready for Inspection ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 8/14/2024 Not Ready for Inspection ASHLEY THOMPSON
Wood Frame 8/14/2024 Corrections Issued ASHLEY THOMPSON
Interior/Exterior Lathing 8/20/2024 Partial Approval ASHLEY THOMPSON
Insulation 8/22/2024 Approved REGINA MENDEZ
Insulation 8/22/2024 Partial Approval ASHLEY THOMPSON
BUILDING-Rough-Frame 9/11/2024 Conditional Approval ASHLEY THOMPSON
Drywall Nailing 9/11/2024 Approved ASHLEY THOMPSON
Green Building Rough 9/11/2024 Approved ASHLEY THOMPSON
METHANE-Rough 9/11/2024 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 11/13/2024 Approved REGINA MENDEZ
Shower Pan 11/13/2024 Not Ready for Inspection REGINA MENDEZ
Shower Pan 11/22/2024 Not Ready for Inspection ASHLEY THOMPSON
Shower Pan 11/26/2024 Approved SEAN HAUPT
Sewer 12/2/2024 Corrections Issued ASHLEY THOMPSON
Shower Pan 12/2/2024 Approved ASHLEY THOMPSON
Sewer 12/6/2024 Approved SEAN HAUPT
Gas Test 1/8/2025 Approved ARAM AVEDISIAN