2710 W FLORENCE AVE 90043
Certificate Information: 2710 W FLORENCE AVE 90043
- Application / Permit
- 22016-10000-14497
- Plan Check / Job No.
- B22LA08982
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- (ePlan) RESTORING FIRE DAMAGED SECOND FLOOR LEVEL "COMPLY WITH DEPARTMENT ORDER effective date 06/13/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 2/8/2023
- Issuing Office
- Current Status
- Permit Finaled on 11/6/2024
Permit Application Status History
| Submitted | 5/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/16/2022 | YOUNG KIM |
| Corrections Issued | 6/24/2022 | YOUNG KIM |
| Quality Review Completed | 7/1/2022 | FARUK SEZER |
| Applicant returned to address corrections | 8/17/2022 | YOUNG KIM |
| Applicant returned to address corrections | 9/15/2022 | YOUNG KIM |
| Plan Check Approved | 9/29/2022 | YOUNG KIM |
| Issued | 2/8/2023 | APPLICANT |
| Permit Finaled | 11/5/2024 | CHRISTOPHER BLACKWOOD |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 7/11/2022 | MAX LODER |
| Redevelopment Project Area | Cleared | 7/20/2022 | GRACIELA ACOSTA |
| DAS Clearance | Cleared | 7/28/2022 | Hernan Arreola |
Contact Information
| Contractor | Corro Carlito Y; Lic. No.: 524225-B | , |
| Contractor | Corro Construction; Lic. No.: 524225-B | , |
| Engineer | Castillo, Engineering; Lic. No.: C91046 | 5164 N RATON CIR LONG BEACH, CA 90807 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2023 | No Access for Inspection | MARTIN TAVITIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/4/2023 | Not Ready for Inspection | DARRYL ARNOLD |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2023 | Approved | MARTIN TAVITIAN |
| Wood Frame | 8/1/2023 | Partial Approval | MARTIN TAVITIAN |
| Interior/Exterior Lathing | 8/17/2023 | Partial Approval | ALAN MORELOS |
| Wood Frame | 12/13/2023 | Not Ready for Inspection | LUIS CCAMACHO |
| Wood Frame | 12/14/2023 | Partial Inspection | LUIS CCAMACHO |
| Insulation | 12/19/2023 | Partial Approval | LUIS CCAMACHO |
| Drywall Nailing | 1/9/2024 | Partial Approval | LUIS CCAMACHO |
| Interior/Exterior Lathing | 1/25/2024 | Partial Approval | LUIS CCAMACHO |
| Final | 4/30/2024 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 4/30/2024 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 4/30/2024 | Not Ready for Inspection | DARRYL ARNOLD |
| Final | 11/1/2024 | Not Ready for Inspection | DARRYL ARNOLD |
| Interior/Exterior Lathing | 11/1/2024 | Corrections Issued | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 11/1/2024 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 11/1/2024 | Approved | DARRYL ARNOLD |
| Final | 11/5/2024 | Permit Finaled | CHRISTOPHER BLACKWOOD |
| SGSOV-Seismic Gas S/O Valve | 11/5/2024 | SGSOV Not Required | CHRISTOPHER BLACKWOOD |