312 S RIMPAU BLVD 90020
Certificate Information: 312 S RIMPAU BLVD 90020
- Application / Permit
- 22016-10000-14392
- Plan Check / Job No.
- B22LA08900
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF (E) 2-STORY GARAGE AND GUEST-HOUSE TO ADU PER STATE LAW. SEE COMMENTS
- Permit Issued
- Issued on 1/22/2024
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 1/22/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/18/2022 | KHUONG TRUONG |
| Corrections Issued | 5/18/2022 | KHUONG TRUONG |
| Building Plans Picked Up | 5/26/2022 | APPLICANT |
| Applicant returned to address corrections | 11/22/2022 | JOSEPH RAFOLS |
| Plan Check Approved | 12/12/2023 | DANIEL SANJUAN |
| Issued | 1/22/2024 | APPLICANT |
Permit Application Clearance Information
| CPC | Cleared | 8/30/2022 | SUKI GERSHENHORN |
| HPOZ | Cleared | 8/30/2022 | SUKI GERSHENHORN |
| Construction near power lines | Cleared | 10/7/2022 | RIDWAN HARDY |
| Address approval | Cleared | 11/14/2022 | TREVOR QUAN |
| Sewer availability | Cleared | 11/14/2022 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 11/21/2022 | ABEL CASILLAS |
Contact Information
| Architect | Williams,, Noel C; Lic. No.: C33223 | 810 SOUTH FLOWER STREET UNIT 213 LOS ANGELES, CA 90017 |
| Contractor | R B Remodeling & Construction; Lic. No.: 905605-B | 433 SOUTH CITRUS AVE LOS ANGELES, CA 90036 |
| Engineer | Erdelyi,, Peter Tibor; Lic. No.: C26962 | 2999 OVERLAND AVE STE 103 LOS ANGELES, CA 90064 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/29/2024 | Corrections Issued | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2024 | Corrections Issued | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2024 | Corrections Issued | RONNIE MINDANAO |
| HVAC-Rough | 5/24/2024 | Not Ready for Inspection | RICHARD DOCKUS |
| PLUMBING-Rough | 5/24/2024 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Rough | 6/7/2024 | Approved | RICHARD DOCKUS |
| HVAC-Rough | 6/7/2024 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 6/12/2024 | Not Ready for Inspection | RICHARD DOCKUS |
| Green Building Rough | 6/12/2024 | Not Ready for Inspection | RICHARD DOCKUS |
| PLUMBING-Rough | 6/12/2024 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 6/27/2024 | Approved | RONNIE MINDANAO |
| Excavation/Setback/Form/Re-Bar | 6/27/2024 | Approved | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Green Building Rough | 6/27/2024 | Approved | RONNIE MINDANAO |
| Interior/Exterior Lathing | 6/27/2024 | Partial Approval | RONNIE MINDANAO |
| METHANE-Rough | 6/27/2024 | Approved | RONNIE MINDANAO |
| Wood Frame | 6/27/2024 | Approved | RONNIE MINDANAO |
| Insulation | 7/1/2024 | Conditional Approval | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 7/9/2024 | Approved | RONNIE MINDANAO |
| Drywall Nailing | 7/12/2024 | Approved | RONNIE MINDANAO |
| Interior/Exterior Lathing | 8/14/2024 | Approved | RONNIE MINDANAO |
| Shower Pan | 8/14/2024 | Approved | RONNIE MINDANAO |
| Deputy Wood Construction | 2/5/2025 | Conditional Approval | RONNIE MINDANAO |
| ELECTRICAL-Final | 2/5/2025 | Corrections Issued | RONNIE MINDANAO |
| Final | 2/5/2025 | Corrections Issued | RONNIE MINDANAO |
| Green Building Final | 2/5/2025 | Approved | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 2/5/2025 | SGSOV Not Ready | RONNIE MINDANAO |
| Smoke Detectors | 2/5/2025 | Approved | RONNIE MINDANAO |
| Final | 3/10/2026 | Corrections Issued | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 3/10/2026 | SGSOV Approved | RONNIE MINDANAO |
| Final | 3/25/2026 | Not Ready for Inspection | RONNIE MINDANAO |