616 N WESTERN AVE 90004

Certificate Information: 616 N WESTERN AVE 90004

Application / Permit
22016-10000-14221
Plan Check / Job No.
B22LA08779
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
TENANT IMPROVEMENT TO EXISTING 3500 SF RETAIL NO CHANGE OF USE. ADD NEW RESTROOM AT THE REAR.
Permit Issued
Issued on 9/16/2022
Issuing Office
Metro
Current Status
Permit Finaled on 5/3/2023

Permit Application Status History

Submitted 5/10/2022 APPLICANT
Assigned to Plan Check Engineer 5/26/2022 QUAN NGHIEM
Corrections Issued 5/27/2022 QUAN NGHIEM
Quality Review Completed 6/8/2022 KEN GILL
Building Plans Picked Up 6/9/2022 APPLICANT
Disabled Access Plans Picked Up 6/22/2022 APPLICANT
Green Plans Picked Up 8/1/2022 APPLICANT
Applicant returned to address corrections 8/17/2022 QUAN NGHIEM
Plan Check Approved 9/7/2022 QUAN NGHIEM
Issued 9/16/2022 APPLICANT
Permit Finaled 5/3/2023 LARRY ARNICK

Permit Application Clearance Information

Redevelopment Project Area Cleared 6/24/2022 DAVID URITA
Green Code Cleared 8/11/2022 DONALD CRICHLOW
DAS Clearance Cleared 8/16/2022 QUAN NGHIEM

Contact Information

Architect Morris,, Peter Lloyd; Lic. No.: C32096 15615 ALTON PARKWAY SUITE 125      IRVINE, CA 92618
Contractor Mata Contracting Corporation; Lic. No.: 966590-B 318 EAST GLENOAKS BLVD   SUITE 201    GLENDALE, CA 91207
Engineer Chen,, Jeff Y; Lic. No.: S4699 17500 REDHILL AVENUE SUITE 240      IRVINE, CA 92614

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 9/27/2022 Partial Approval RUSSELL BONVOULOIR
Light Gage Steel Frame 10/24/2022 Partial Inspection JONATHAN QUACH
Deputy Wood Construction 10/27/2022 Conditional Approval MICHAEL ROSENBERG
Insulation 10/27/2022 Partial Approval TIMOTHY BUXTON
Light Gage Steel Frame 10/27/2022 Partial Approval TIMOTHY BUXTON
Insulation 10/28/2022 Approved JONATHAN QUACH
Light Gage Steel Frame 10/28/2022 Partial Approval JONATHAN QUACH
Excavation/Setback/Form/Re-Bar 11/2/2022 Partial Approval JONATHAN QUACH
Excavation/Setback/Form/Re-Bar 11/4/2022 Not Ready for Inspection JONATHAN QUACH
Excavation/Setback/Form/Re-Bar 11/10/2022 Approved JONATHAN QUACH
Footing/Foundation/Slab 11/10/2022 Approved JONATHAN QUACH
Deputy Drilled-In Anchors 11/14/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 11/17/2022 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 11/23/2022 Not Ready for Inspection EDWIN GREGORYONA
Drywall Nailing 11/29/2022 Partial Inspection ALFREDO LOPEZ
Insulation 12/12/2022 Not Ready for Inspection RAFAEL CORTES
Deputy Wood Construction 12/15/2022 Conditional Approval RAFAEL CORTES
Light Gage Steel Frame 12/15/2022 Partial Approval RAFAEL CORTES
Insulation 12/20/2022 Partial Approval RONALD JIMENEZ
Interior/Exterior Lathing 12/20/2022 Partial Approval RONALD JIMENEZ
Interior/Exterior Lathing 12/23/2022 Corrections Issued RONALD JIMENEZ
Interior/Exterior Lathing 12/29/2022 Not Ready for Inspection TIMOTHY POWELL
Deputy Drilled-In Anchors 1/6/2023 No Access for Inspection RONALD JIMENEZ
Interior/Exterior Lathing 1/6/2023 No Access for Inspection RONALD JIMENEZ
Interior/Exterior Lathing 1/9/2023 Not Ready for Inspection TIMOTHY POWELL
Interior/Exterior Lathing 1/10/2023 Partial Approval TIMOTHY POWELL
Drywall Nailing 1/11/2023 Partial Approval TIMOTHY POWELL
Interior/Exterior Lathing 1/20/2023 Approved RONALD JIMENEZ
Pre-Inspection 2/8/2023 Not Ready for Inspection TIMOTHY POWELL
Special/Order Compliance 2/9/2023 Partial Approval TIMOTHY POWELL
Final 4/25/2023 Partial Inspection TIMOTHY POWELL
Green Building Final 4/25/2023 Not Ready for Inspection TIMOTHY POWELL
Green Building Rough 4/25/2023 Not Ready for Inspection TIMOTHY POWELL
Reinforced Masonry Frame 4/25/2023 Not Ready for Inspection TIMOTHY POWELL
SGSOV-Seismic Gas S/O Valve 4/25/2023 SGSOV Not Ready TIMOTHY POWELL
Smoke Detectors 4/25/2023 Not Ready for Inspection TIMOTHY POWELL
Final 4/26/2023 Conditional Approval LARRY ARNICK
Green Building Final 4/26/2023 Approved LARRY ARNICK
Green Building Rough 4/26/2023 Approved LARRY ARNICK
Reinforced Masonry Frame 4/26/2023 Approved LARRY ARNICK
SGSOV-Seismic Gas S/O Valve 4/26/2023 SGSOV Approved LARRY ARNICK
Smoke Detectors 4/26/2023 Approved LARRY ARNICK
Final 5/3/2023 Permit Finaled LARRY ARNICK