616 N WESTERN AVE 90004
Certificate Information: 616 N WESTERN AVE 90004
- Application / Permit
- 22016-10000-14221
- Plan Check / Job No.
- B22LA08779
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- TENANT IMPROVEMENT TO EXISTING 3500 SF RETAIL NO CHANGE OF USE. ADD NEW RESTROOM AT THE REAR.
- Permit Issued
- Issued on 9/16/2022
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 5/3/2023
Permit Application Status History
| Submitted | 5/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2022 | QUAN NGHIEM |
| Corrections Issued | 5/27/2022 | QUAN NGHIEM |
| Quality Review Completed | 6/8/2022 | KEN GILL |
| Building Plans Picked Up | 6/9/2022 | APPLICANT |
| Disabled Access Plans Picked Up | 6/22/2022 | APPLICANT |
| Green Plans Picked Up | 8/1/2022 | APPLICANT |
| Applicant returned to address corrections | 8/17/2022 | QUAN NGHIEM |
| Plan Check Approved | 9/7/2022 | QUAN NGHIEM |
| Issued | 9/16/2022 | APPLICANT |
| Permit Finaled | 5/3/2023 | LARRY ARNICK |
Permit Application Clearance Information
| Redevelopment Project Area | Cleared | 6/24/2022 | DAVID URITA |
| Green Code | Cleared | 8/11/2022 | DONALD CRICHLOW |
| DAS Clearance | Cleared | 8/16/2022 | QUAN NGHIEM |
Contact Information
| Architect | Morris,, Peter Lloyd; Lic. No.: C32096 | 15615 ALTON PARKWAY SUITE 125 IRVINE, CA 92618 |
| Contractor | Mata Contracting Corporation; Lic. No.: 966590-B | 318 EAST GLENOAKS BLVD SUITE 201 GLENDALE, CA 91207 |
| Engineer | Chen,, Jeff Y; Lic. No.: S4699 | 17500 REDHILL AVENUE SUITE 240 IRVINE, CA 92614 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 9/27/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Light Gage Steel Frame | 10/24/2022 | Partial Inspection | JONATHAN QUACH |
| Deputy Wood Construction | 10/27/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Insulation | 10/27/2022 | Partial Approval | TIMOTHY BUXTON |
| Light Gage Steel Frame | 10/27/2022 | Partial Approval | TIMOTHY BUXTON |
| Insulation | 10/28/2022 | Approved | JONATHAN QUACH |
| Light Gage Steel Frame | 10/28/2022 | Partial Approval | JONATHAN QUACH |
| Excavation/Setback/Form/Re-Bar | 11/2/2022 | Partial Approval | JONATHAN QUACH |
| Excavation/Setback/Form/Re-Bar | 11/4/2022 | Not Ready for Inspection | JONATHAN QUACH |
| Excavation/Setback/Form/Re-Bar | 11/10/2022 | Approved | JONATHAN QUACH |
| Footing/Foundation/Slab | 11/10/2022 | Approved | JONATHAN QUACH |
| Deputy Drilled-In Anchors | 11/14/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 11/17/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Floor/Roof Diaphrgm/Shear Wall | 11/23/2022 | Not Ready for Inspection | EDWIN GREGORYONA |
| Drywall Nailing | 11/29/2022 | Partial Inspection | ALFREDO LOPEZ |
| Insulation | 12/12/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Deputy Wood Construction | 12/15/2022 | Conditional Approval | RAFAEL CORTES |
| Light Gage Steel Frame | 12/15/2022 | Partial Approval | RAFAEL CORTES |
| Insulation | 12/20/2022 | Partial Approval | RONALD JIMENEZ |
| Interior/Exterior Lathing | 12/20/2022 | Partial Approval | RONALD JIMENEZ |
| Interior/Exterior Lathing | 12/23/2022 | Corrections Issued | RONALD JIMENEZ |
| Interior/Exterior Lathing | 12/29/2022 | Not Ready for Inspection | TIMOTHY POWELL |
| Deputy Drilled-In Anchors | 1/6/2023 | No Access for Inspection | RONALD JIMENEZ |
| Interior/Exterior Lathing | 1/6/2023 | No Access for Inspection | RONALD JIMENEZ |
| Interior/Exterior Lathing | 1/9/2023 | Not Ready for Inspection | TIMOTHY POWELL |
| Interior/Exterior Lathing | 1/10/2023 | Partial Approval | TIMOTHY POWELL |
| Drywall Nailing | 1/11/2023 | Partial Approval | TIMOTHY POWELL |
| Interior/Exterior Lathing | 1/20/2023 | Approved | RONALD JIMENEZ |
| Pre-Inspection | 2/8/2023 | Not Ready for Inspection | TIMOTHY POWELL |
| Special/Order Compliance | 2/9/2023 | Partial Approval | TIMOTHY POWELL |
| Final | 4/25/2023 | Partial Inspection | TIMOTHY POWELL |
| Green Building Final | 4/25/2023 | Not Ready for Inspection | TIMOTHY POWELL |
| Green Building Rough | 4/25/2023 | Not Ready for Inspection | TIMOTHY POWELL |
| Reinforced Masonry Frame | 4/25/2023 | Not Ready for Inspection | TIMOTHY POWELL |
| SGSOV-Seismic Gas S/O Valve | 4/25/2023 | SGSOV Not Ready | TIMOTHY POWELL |
| Smoke Detectors | 4/25/2023 | Not Ready for Inspection | TIMOTHY POWELL |
| Final | 4/26/2023 | Conditional Approval | LARRY ARNICK |
| Green Building Final | 4/26/2023 | Approved | LARRY ARNICK |
| Green Building Rough | 4/26/2023 | Approved | LARRY ARNICK |
| Reinforced Masonry Frame | 4/26/2023 | Approved | LARRY ARNICK |
| SGSOV-Seismic Gas S/O Valve | 4/26/2023 | SGSOV Approved | LARRY ARNICK |
| Smoke Detectors | 4/26/2023 | Approved | LARRY ARNICK |
| Final | 5/3/2023 | Permit Finaled | LARRY ARNICK |