4014 W MARCHENA DR 90065
Certificate Information: 4014 W MARCHENA DR 90065
- Application / Permit
- 22016-10000-14111
- Plan Check / Job No.
- B22LA08708
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL TO (E) SFD. EXTERIOR ALTERATIONS INCLUDING WINDOW AND DOOR REPLACEMENT. NEW FRAMING AND FOUNDATION MEMBERS. NEW SKYLIGHTS. (no change in floor area, height) **ORDER TO COMPLY ISSUED ON 5/4/2022**
- Permit Issued
- Issued on 6/13/2022
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 11/3/2022
Permit Application Status History
| Submitted | 5/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/9/2022 | GEORGE ALVAREZ |
| Corrections Issued | 5/9/2022 | GEORGE ALVAREZ |
| Plan Check Approved | 6/13/2022 | AUNG SOE |
| Issued | 6/13/2022 | APPLICANT |
| Permit Finaled | 11/2/2022 | OSVALDO PARAMO |
Permit Application Clearance Information
| Specific Plan | Cleared | 5/27/2022 | NASHYA JENSEN |
| Grading Pre-Inspection | Cleared | 6/7/2022 | KIRK LINKLATER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Papazyan,, Andranik; Lic. No.: C56824 | 635 W COLORADO ST STE 104 GLENDALE, CA 91204 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/16/2022 | Corrections Issued | OSVALDO PARAMO |
| Footing/Foundation/Slab | 6/22/2022 | Approved | OSVALDO PARAMO |
| Deputy Drilled-In Anchors | 6/23/2022 | Conditional Approval | OSVALDO PARAMO |
| PLUMBING-Rough | 6/29/2022 | Approved | OSVALDO PARAMO |
| HVAC-Rough | 7/5/2022 | Approved | OSVALDO PARAMO |
| Shower Pan | 7/6/2022 | Approved | OSVALDO PARAMO |
| Wood Frame | 7/6/2022 | Approved | OSVALDO PARAMO |
| Insulation | 7/11/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| Interior/Exterior Lathing | 7/11/2022 | Partial Approval | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 7/13/2022 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Rough | 7/13/2022 | Approved | OSVALDO PARAMO |
| Insulation | 7/13/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| Insulation | 7/22/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Insulation | 7/26/2022 | Approved | AMY COLIN |
| Drywall Nailing | 7/29/2022 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 7/29/2022 | Partial Approval | OSVALDO PARAMO |
| Interior/Exterior Lathing | 8/5/2022 | Approved | OSVALDO PARAMO |
| PLUMBING-Final | 10/13/2022 | Corrections Issued | OSVALDO PARAMO |
| ELECTRICAL-Final | 10/14/2022 | Corrections Issued | OSVALDO PARAMO |
| HVAC-Final | 10/17/2022 | Approved | OSVALDO PARAMO |
| Final | 10/21/2022 | Corrections Issued | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 10/21/2022 | SGSOV Approved | OSVALDO PARAMO |
| Smoke Detectors | 10/21/2022 | Approved | OSVALDO PARAMO |
| Final | 11/2/2022 | Permit Finaled | OSVALDO PARAMO |