7009 1/2 S 4TH AVE 90043

Certificate Information: 7009 1/2 S 4TH AVE 90043

Application / Permit
22016-10000-14045
Plan Check / Job No.
B22LA08645
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan Convert Existing 2 Detached Garage to ADU. PER STATE LAW
Permit Issued
Issued on 8/31/2022
Issuing Office
Current Status
CofO Issued on 8/22/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/11/2022 APPLICANT
Assigned to Plan Check Engineer 5/15/2022 KHUONG TRUONG
Corrections Issued 5/17/2022 KHUONG TRUONG
Plan Check Approved 8/5/2022 KHUONG TRUONG
Issued 8/31/2022 APPLICANT
CofO in Progress 8/16/2023 ENRIQUE MIRELES
CofO in Progress 8/16/2023 ENRIQUE MIRELES
Permit Finaled 8/22/2023 DEROLD HAUFF
CofO Issued 8/22/2023 DEROLD HAUFF
Permit Finaled 8/22/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/2/2022 WALLIE JONG
Sewer availability Cleared 6/2/2022 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 6/7/2022 WALLIE JONG
Tenant Habitability Plan Cleared 6/14/2022 ISMAEL HERNANDEZ
Construction near power lines Cleared 7/23/2022 RIDWAN HARDY

Contact Information

Contractor Ariel Muller; Lic. No.: 1026822-B       ,
Engineer Wassef,, Mena; Lic. No.: C84979 28131 VALERIO CT      VALENCIA, CA 91354

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/23/2022 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 10/21/2022 Approved RYAN SALAZAR
Sewer 11/29/2022 Approved ENRIQUE MIRELES
Gas Test 1/4/2023 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 1/18/2023 Partial Approval ENRIQUE MIRELES
PLUMBING-Rough 1/18/2023 Partial Approval ENRIQUE MIRELES
Wood Frame 1/18/2023 Partial Approval ENRIQUE MIRELES
Insulation 2/6/2023 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 2/21/2023 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 2/21/2023 Approved ENRIQUE MIRELES
Drywall Nailing 3/1/2023 Not Ready for Inspection ENRIQUE MIRELES
Drywall Nailing 3/13/2023 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 5/2/2023 Corrections Issued ENRIQUE MIRELES
Interior/Exterior Lathing 5/5/2023 Approved ENRIQUE MIRELES
Final 6/26/2023 Partial Inspection ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 6/26/2023 SGSOV Approved ENRIQUE MIRELES
Service/Power Release 6/26/2023 Approved ENRIQUE MIRELES
Smoke Detectors 6/26/2023 Not Ready for Inspection ENRIQUE MIRELES
Final 8/3/2023 Corrections Issued ENRIQUE MIRELES
Service/Power Release 8/3/2023 Approved ENRIQUE MIRELES
Smoke Detectors 8/3/2023 Approved ENRIQUE MIRELES
Final 8/15/2023 OK to Issue CofO ENRIQUE MIRELES
Service/Power Release 8/15/2023 Approved ENRIQUE MIRELES