659-661 1/2 N IMOGEN AVE 90026
Certificate Information: 659-661 1/2 N IMOGEN AVE 90026
- Application / Permit
- 22016-10000-13962
- Plan Check / Job No.
- B22LA08588
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- ePlan PROPOSED INTERIOR REMODELING OF 2 FIRST FLOOR UNITS(659 &661) OF EXISTING 4 UNITS APARTMENT BUILDING . NEW PARTITIONS AND WINDOWS.
- Permit Issued
- Issued on 10/14/2022
- Issuing Office
- Current Status
- Permit Finaled on 11/13/2023
Permit Application Status History
| Submitted | 5/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/13/2022 | SAMUEL GONZALEZ |
| Corrections Issued | 5/14/2022 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 6/15/2022 | SAMUEL GONZALEZ |
| Plan Check Approved | 7/18/2022 | SAMUEL GONZALEZ |
| No Progress | 10/5/2022 | SAMUEL GONZALEZ |
| Plan Check Approved | 10/14/2022 | SAMUEL GONZALEZ |
| Issued | 10/14/2022 | APPLICANT |
| Permit Finaled | 11/13/2023 | RONALD JIMENEZ |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 6/21/2022 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Bahman Keyvani; Lic. No.: 923783-B | , |
| Contractor | Keyvani Bahman; Lic. No.: 923783-B | , |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 11/18/2022 | Corrections Issued | GREGORY POMISH |
| Interior/Exterior Lathing | 1/24/2023 | Corrections Issued | TIMOTHY POWELL |
| Interior/Exterior Lathing | 1/26/2023 | Not Ready for Inspection | TIMOTHY POWELL |
| Wood Frame | 3/15/2023 | Not Ready for Inspection | TIMOTHY POWELL |
| Wood Frame | 4/10/2023 | Partial Approval | TIMOTHY POWELL |
| Drywall Nailing | 4/21/2023 | Partial Approval | RONALD JIMENEZ |
| Wood Frame | 4/21/2023 | Approved | RONALD JIMENEZ |
| Wood Frame | 4/26/2023 | Partial Inspection | TIMOTHY POWELL |
| Insulation | 5/4/2023 | Partial Approval | TIMOTHY POWELL |
| Insulation | 5/10/2023 | Approved | TIMOTHY POWELL |
| Drywall Nailing | 5/16/2023 | Approved | VAHE KELEDJIAN |
| Final | 9/19/2023 | Conditional Approval | RONALD JIMENEZ |
| SGSOV-Seismic Gas S/O Valve | 9/19/2023 | SGSOV Approved | RONALD JIMENEZ |
| Smoke Detectors | 9/19/2023 | Approved | RONALD JIMENEZ |
| Final | 11/13/2023 | Permit Finaled | RONALD JIMENEZ |