612 E MONTECITO DR 90031

Certificate Information: 612 E MONTECITO DR 90031

Application / Permit
22016-10000-13804
Plan Check / Job No.
B22LA08488
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan CONVERT EXISTING ATTACHED 2-CAR GARAGE TO ADU - 622 SF PER CA GOV'T CODE 65852.2(e)(1)(A)
Permit Issued
Issued on 7/1/2022
Issuing Office
Current Status
Issued on 7/1/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/5/2022 APPLICANT
Assigned to Plan Check Engineer 5/12/2022 HANS SANTIAGO
Corrections Issued 5/13/2022 HANS SANTIAGO
Plan Check Approved 6/1/2022 ANDREW SANTIAGO
Issued 7/1/2022 APPLICANT

Permit Application Clearance Information

Address approval Cleared 5/19/2022 STEVE MELGAR
Sewer availability Cleared 5/19/2022 STEVE MELGAR
Grading Pre-Inspection Cleared 5/20/2022 KIRK LINKLATER
Eng Process Fee Ord 176,300 Cleared 5/23/2022 STEVE MELGAR
"Q" conditions Cleared 5/26/2022 MAXFIELD VERMY

Contact Information

Contractor Owner-Builder       ,
Engineer Nagovitsyn,, Evgeny; Lic. No.: C93527 17436 ARMINTA ST      NORTHRIDGE, CA 91325

Inspector Information

THOMAS WILLIS, (213) 252-3038 Office Hours: 7:00-8:00 AM MON-FRI
JEFFREY CHRISTIAN, (213) 252-3038 Office Hours: 7:00-8:00 AM MON-FRI
FERMIN RUBIO, (213) 252-3038 Office Hours: 7:00-8:00 AM MON-FRI
JACOB SEGURA, (213) 252-3038 Office Hours: 7:00-8:00 AM MON-FRI
CLAUDIO MORENO, (213) 252-3038 Office Hours: 7:00-8:00 AM MON-FRI
MARK RUDE, (213) 252-3038 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 12/9/2024 Not Ready for Inspection JACOB SEGURA
Notice of Violation 12/9/2024 Not Required JACOB SEGURA
Pre-Inspection 12/9/2024 No Access for Inspection JACOB SEGURA
Wood Frame 12/9/2024 Not Ready for Inspection JACOB SEGURA
BUILDING-Rough-Frame 12/13/2024 Not Ready for Inspection JACOB SEGURA
Footing/Foundation/Slab 12/13/2024 Corrections Issued JACOB SEGURA
Green Building Rough 12/13/2024 Not Ready for Inspection JACOB SEGURA
Pre-Inspection 12/13/2024 Approved JACOB SEGURA
Wood Frame 12/13/2024 Not Ready for Inspection JACOB SEGURA