227 N LARCHMONT BLVD 90004
Certificate Information: 227 N LARCHMONT BLVD 90004
- Application / Permit
- 22016-10000-13762
- Plan Check / Job No.
- B22LA08458
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant - Take Out
- Work Description
- ePlan New Take-out / To-go restaurant (no seating / retail sales only) in existing retail building. New Accessible Restrooms, New Kitchen, New Customer Order Counter. No change to parking.
- Permit Issued
- Issued on 2/15/2023
- Issuing Office
- Current Status
- CofO Issued on 7/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/15/2022 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 5/16/2022 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 1/3/2023 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 2/14/2023 | FARSHAD ALIMOHAMADI |
| Issued | 2/15/2023 | APPLICANT |
| CofO in Progress | 7/7/2023 | ERNESTO CORRAL |
| Permit Finaled | 7/7/2023 | ERNESTO CORRAL |
| CofO Issued | 7/7/2023 | ERNESTO CORRAL |
Permit Application Clearance Information
| "D" conditions | Cleared | 8/18/2022 | JAZMIN ROQUE |
| Eng Process Fee Ord 176,300 | Cleared | 9/1/2022 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 9/1/2022 | CHRISTOPHER ROCHA |
| "Q" conditions | Cleared | 9/7/2022 | JAZMIN ROQUE |
| CPC | Cleared | 9/7/2022 | JAZMIN ROQUE |
| Food Service Establishment | Cleared | 2/14/2023 | KENNETH BROWNE |
| Food establishment approval | Cleared | 2/14/2023 | LACDHS APPROVED |
Contact Information
| Contractor | Calasia Construction Inc; Lic. No.: 938255-B | , |
| Engineer | Louks,, Daniel Robert; Lic. No.: NA56332 | , |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/16/2023 | Approved | ALAN MORELOS |
| Light Gage Steel Frame | 3/13/2023 | Partial Approval | JEROME BLACKWOOD |
| Pre-Inspection | 3/13/2023 | Partial Approval | JEROME BLACKWOOD |
| Special/Order Compliance | 3/14/2023 | Partial Inspection | GREGORY POMISH |
| Footing/Foundation/Slab | 3/16/2023 | Partial Approval | JEROME BLACKWOOD |
| Insulation | 3/16/2023 | Approved | JEROME BLACKWOOD |
| Light Gage Steel Frame | 3/16/2023 | Partial Approval | JEROME BLACKWOOD |
| Deputy Drilled-In Anchors | 3/22/2023 | No Access for Inspection | ALFREDO LOPEZ |
| Drywall Nailing | 3/31/2023 | Partial Approval | ALFREDO LOPEZ |
| Structural Steel Frame | 3/31/2023 | Partial Approval | ALFREDO LOPEZ |
| Light Gage Steel Frame | 4/5/2023 | Partial Approval | JEROME BLACKWOOD |
| Light Gage Steel Frame | 4/27/2023 | Partial Approval | JEROME BLACKWOOD |
| T-Bar Ceiling | 4/27/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Drywall Nailing | 5/1/2023 | Approved | JULIAN CAPUCETTI |
| T-Bar Ceiling | 5/1/2023 | Approved | JULIAN CAPUCETTI |
| Posting Pre-Inspection | 6/16/2023 | Partial Approval | JEROME BLACKWOOD |
| Final | 6/20/2023 | Conditional Approval | JEROME BLACKWOOD |
| METHANE-Final | 6/20/2023 | Approved | JEROME BLACKWOOD |
| METHANE-Rough | 6/20/2023 | Approved | JEROME BLACKWOOD |
| Reinforced Masonry Frame | 6/20/2023 | Approved | JEROME BLACKWOOD |
| SGSOV-Seismic Gas S/O Valve | 6/20/2023 | SGSOV Approved | JEROME BLACKWOOD |
| Smoke Detectors | 6/20/2023 | Approved | JEROME BLACKWOOD |