9020 S BELLANCA AVE 90045
Certificate Information: 9020 S BELLANCA AVE 90045
- Application / Permit
- 22016-10000-13473
- Plan Check / Job No.
- B22LA08281
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (8) Automobile Body & Fender Repairing
- Work Description
- ePlan: Change of use of (E) retail building to an Auto Body Repair Shop with a spray-paint booth & Exterior & Interior T.I & re-striping the parking lot
- Permit Issued
- Issued on 7/20/2023
- Issuing Office
- Current Status
- CofO Issued on 1/4/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/2/2022 | GARO TELMI |
| Corrections Issued | 6/28/2022 | GARO TELMI |
| Quality Review Completed | 7/1/2022 | CHAD DOI |
| Applicant returned to address corrections | 9/9/2022 | GARO TELMI |
| Applicant returned to address corrections | 10/12/2022 | GARO TELMI |
| Applicant returned to address corrections | 10/18/2022 | GARO TELMI |
| Applicant returned to address corrections | 12/9/2022 | GARO TELMI |
| Applicant returned to address corrections | 1/5/2023 | GARO TELMI |
| Applicant returned to address corrections | 1/12/2023 | GARO TELMI |
| Applicant returned to address corrections | 3/26/2023 | GARO TELMI |
| Applicant returned to address corrections | 4/20/2023 | GARO TELMI |
| Applicant returned to address corrections | 6/26/2023 | GARO TELMI |
| Applicant returned to address corrections | 7/2/2023 | GARO TELMI |
| Applicant returned to address corrections | 7/8/2023 | GARO TELMI |
| Applicant returned to address corrections | 7/16/2023 | GARO TELMI |
| Plan Check Approved | 7/20/2023 | GARO TELMI |
| Issued | 7/20/2023 | APPLICANT |
| CofO in Progress | 1/2/2024 | GRANT WOODS |
| Permit Finaled | 1/4/2024 | DAVID TSAU |
| CofO Issued | 1/4/2024 | DAVID TSAU |
| Permit Finaled | 1/4/2024 | DAVID TSAU |
Permit Application Clearance Information
| Green Code | Cleared | 7/6/2022 | AARON COSTA |
| Metro Rail approval | Cleared | 12/13/2022 | GARO TELMI |
| DAS Clearance | Cleared | 12/14/2022 | Hernan Arreola |
| Eng Process Fee Ord 176,300 | Cleared | 1/25/2023 | AHMED AMARRAGY |
| Miscellaneous | Cleared | 1/25/2023 | AHMED AMARRAGY |
| Sewer availability | Cleared | 1/25/2023 | AHMED AMARRAGY |
| Specific Plan | Cleared | 4/10/2023 | PEDRO AYALA |
| Automotive Use | Cleared | 6/16/2023 | MAXFIELD VERMY |
| Miscellaneous | Cleared | 6/16/2023 | MAXFIELD VERMY |
| Prkng lot landscape/Water mgmt | Cleared | 6/16/2023 | MAXFIELD VERMY |
| ZA Case | Cleared | 6/16/2023 | MAXFIELD VERMY |
| ZA Case | Cleared | 6/16/2023 | MAXFIELD VERMY |
| Body shop | Cleared | 7/10/2023 | SCAQMD APPROVED |
| Spray-paint booth | Cleared | 7/10/2023 | SCAQMD APPROVED |
Contact Information
| Architect | Carne,, Daniel D; Lic. No.: C10251 | 3770 SLEEPY HOLLOW DRIVE RENO, NV 89502 |
| Contractor | Rely-On Spray Booth Co Inc; Lic. No.: 506096-B | , |
| Contractor | Rely-On Technologies; Lic. No.: 506096-B | , |
| Engineer | Kaiser,, Mark; Lic. No.: S5887 | 12001 N CENTRAL EXPRESSWAY 300 DALLAS, TX 75243 |
Inspector Information
| DANIEL ARMENTA, (310) 914-3925 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 7/26/2023 | Corrections Issued | GRANT WOODS |
| Excavation/Setback/Form/Re-Bar | 7/27/2023 | Partial Approval | GRANT WOODS |
| Excavation/Setback/Form/Re-Bar | 7/31/2023 | Partial Approval | ALAN NOVAK |
| Deputy Drilled-In Anchors | 8/3/2023 | Approved | GRANT WOODS |
| Excavation/Setback/Form/Re-Bar | 8/3/2023 | Partial Approval | GRANT WOODS |
| Deputy Drilled-In Anchors | 8/10/2023 | Conditional Approval | GRANT WOODS |
| Deputy Steel/Welding | 8/10/2023 | Conditional Approval | GRANT WOODS |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2023 | Corrections Issued | GRANT WOODS |
| Floor/Roof Diaphrgm/Shear Wall | 8/11/2023 | Partial Approval | GRANT WOODS |
| Green Building Rough | 9/1/2023 | Approved | GRANT WOODS |
| Wood Frame | 9/1/2023 | Not Ready for Inspection | GRANT WOODS |
| Wood Frame | 9/8/2023 | Corrections Issued | GRANT WOODS |
| Drywall Nailing | 9/19/2023 | Partial Approval | GRANT WOODS |
| Drywall Nailing | 9/26/2023 | Partial Approval | GRANT WOODS |
| Special/Order Compliance | 10/3/2023 | Partial Approval | GRANT WOODS |
| Deputy Drilled-In Anchors | 10/5/2023 | Conditional Approval | GRANT WOODS |
| Deputy Drilled-In Anchors | 10/6/2023 | Conditional Approval | GRANT WOODS |
| Deputy Steel/Welding | 10/6/2023 | Conditional Approval | GRANT WOODS |
| Wood Frame | 10/6/2023 | Partial Approval | JOEY BUCHANAN |
| Excavation/Setback/Form/Re-Bar | 10/13/2023 | Not Ready for Inspection | GRANT WOODS |
| Structural Steel Frame | 10/27/2023 | Not Ready for Inspection | GRANT WOODS |
| Deputy Drilled-In Anchors | 10/31/2023 | Conditional Approval | GRANT WOODS |
| Deputy Drilled-In Anchors | 11/2/2023 | Conditional Approval | GRANT WOODS |
| Deputy Steel/Welding | 11/2/2023 | Conditional Approval | GRANT WOODS |
| Final | 11/3/2023 | Partial Inspection | GRANT WOODS |
| Green Building Final | 11/3/2023 | Not Ready for Inspection | GRANT WOODS |
| Reinforced Masonry Frame | 11/3/2023 | Not Ready for Inspection | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 11/3/2023 | SGSOV Not Ready | GRANT WOODS |
| Smoke Detectors | 11/3/2023 | Not Ready for Inspection | GRANT WOODS |
| Wood Frame | 11/3/2023 | Not Ready for Inspection | GRANT WOODS |
| Footing/Foundation/Slab | 12/8/2023 | Approved | ALAN NOVAK |
| Final | 12/19/2023 | Conditional Approval | GRANT WOODS |
| Green Building Final | 12/19/2023 | Approved | GRANT WOODS |
| Reinforced Masonry Frame | 12/19/2023 | Approved | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 12/19/2023 | SGSOV Approved | GRANT WOODS |
| Smoke Detectors | 12/19/2023 | Approved | GRANT WOODS |
| Wood Frame | 12/19/2023 | Approved | GRANT WOODS |