1731 S BRONSON AVE 90019
Certificate Information: 1731 S BRONSON AVE 90019
- Application / Permit
- 22016-10000-13365
- Plan Check / Job No.
- B22LA08215
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF PART OF THE GARAGE PLUS AN ADDITION TO AN ADU. 1-CARE GARAGE TO REMAIN
- Permit Issued
- Issued on 7/8/2022
- Issuing Office
- Current Status
- CofO Issued on 5/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/13/2022 | JOE VO |
| Corrections Issued | 5/14/2022 | JOE VO |
| Applicant returned to address corrections | 6/6/2022 | JOE VO |
| Plan Check Approved | 7/8/2022 | JOE VO |
| Issued | 7/8/2022 | APPLICANT |
| CofO in Progress | 5/16/2023 | CALEB MEISTER |
| Permit Finaled | 5/21/2023 | DEROLD HAUFF |
| CofO Issued | 5/21/2023 | DEROLD HAUFF |
| Permit Finaled | 5/21/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/26/2022 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 5/26/2022 | JEANIE LAM |
| Sewer availability | Cleared | 5/31/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 6/2/2022 | JEANIE LAM |
| Community Plan Implem. Overlay | Cleared | 6/30/2022 | KYLE WINSTON |
Contact Information
| Contractor | Neo Builders Inc; Lic. No.: 1061134-B | , |
| Engineer | Crook,, Barrett Cameron; Lic. No.: NA57196 | , |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/30/2022 | Corrections Issued | STUART CHAPMAN |
| Footing/Foundation/Slab | 9/30/2022 | Not Ready for Inspection | STUART CHAPMAN |
| METHANE-Barrier | 9/30/2022 | Approved | STUART CHAPMAN |
| METHANE-Subgrade | 9/30/2022 | Approved | STUART CHAPMAN |
| Sewer | 9/30/2022 | Approved | STUART CHAPMAN |
| Underground Mechanical | 9/30/2022 | Partial Approval | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 10/28/2022 | Approved | STUART CHAPMAN |
| Footing/Foundation/Slab | 10/28/2022 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 11/7/2022 | Partial Approval | STUART CHAPMAN |
| Wood Frame | 11/7/2022 | Partial Approval | STUART CHAPMAN |
| Insulation | 11/10/2022 | Partial Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2022 | Partial Approval | STUART CHAPMAN |
| BUILDING-Rough-Frame | 12/27/2022 | Corrections Issued | CALEB MEISTER |
| ELECTRICAL-Rough | 12/27/2022 | Corrections Issued | CALEB MEISTER |
| Green Building Rough | 12/27/2022 | Not Ready for Inspection | CALEB MEISTER |
| HVAC-Rough | 12/27/2022 | Approved | CALEB MEISTER |
| METHANE-Rough | 12/27/2022 | Approved | CALEB MEISTER |
| PLUMBING-Rough | 12/27/2022 | Approved | CALEB MEISTER |
| Deputy Wood Construction | 12/28/2022 | Conditional Approval | FREDDIE RIVERA |
| Deputy Reinf. Concrete | 12/30/2022 | Conditional Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 1/4/2023 | Approved | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 1/4/2023 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 1/4/2023 | Partial Approval | CALEB MEISTER |
| Wood Frame | 1/4/2023 | Approved | CALEB MEISTER |
| Insulation | 1/9/2023 | Conditional Approval | MICHAEL LEWIS |
| Drywall Nailing | 1/17/2023 | Partial Approval | CALEB MEISTER |
| Interior/Exterior Lathing | 1/17/2023 | Approved | CALEB MEISTER |
| BUILDING-Rough-Frame | 3/30/2023 | Approved | CALEB MEISTER |
| ELECTRICAL-Final | 3/30/2023 | Corrections Issued | CALEB MEISTER |
| Final | 3/30/2023 | Corrections Issued | CALEB MEISTER |
| Gas Test | 3/30/2023 | Approved | CALEB MEISTER |
| Green Building Final | 3/30/2023 | Not Ready for Inspection | CALEB MEISTER |
| Green Building Rough | 3/30/2023 | Approved | CALEB MEISTER |
| HVAC-Final | 3/30/2023 | Corrections Issued | CALEB MEISTER |
| PLUMBING-Final | 3/30/2023 | Corrections Issued | CALEB MEISTER |
| SGSOV-Seismic Gas S/O Valve | 3/30/2023 | SGSOV Approved | CALEB MEISTER |
| Smoke Detectors | 3/30/2023 | Approved | CALEB MEISTER |
| Final | 4/14/2023 | Not Ready for Inspection | CALEB MEISTER |
| Green Building Final | 4/14/2023 | Approved | CALEB MEISTER |
| Final | 5/16/2023 | OK to Issue CofO | CALEB MEISTER |