1534 S SHENANDOAH ST 90035
Certificate Information: 1534 S SHENANDOAH ST 90035
- Application / Permit
- 22016-10000-13360
- Plan Check / Job No.
- B22LA08214
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- TO VERIFY WORK DONE UNDER PROPOSED ADU CONVERSION PERMIT# 21016-20000-16217 USING WOOD SHEAR WALL MEETS THE MINIMUM REQUIREMENTS OF SOFT-STORY RETROFIT ORDINANCE PER LABC CHAPTER 93.**CERTIFICATE OF COMPLAINCE FOR SOFT STORY SHALL NOT BE ISSUED TILL CERTIFICATE OF OCCUPANCY FOR ADU PERMIT IS OBTAINED**
- Permit Issued
- Issued on 1/27/2023
- Issuing Office
- Metro
- Current Status
- CofC Issued on 12/19/2025
Permit Application Status History
| Submitted | 5/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/12/2022 | HANS SANTIAGO |
| Corrections Issued | 5/17/2022 | HANS SANTIAGO |
| Quality Review Completed | 5/17/2022 | SAI KHUM |
| Building Plans Picked Up | 5/18/2022 | APPLICANT |
| Applicant returned to address corrections | 10/20/2022 | HANS SANTIAGO |
| Plan Check Approved | 1/12/2023 | ANDREW SANTIAGO |
| Issued | 1/27/2023 | APPLICANT |
| OK for CofC | 8/6/2024 | DARRYL ARNOLD |
| CofC Issued | 12/19/2025 | ERNESTO CORRAL |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 1/24/2023 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Quakestrong; Lic. No.: 1037437-B | 1213 LA BREA AVENUE LOS ANGELES, CA 90019 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/30/2023 | Partial Approval | FARHAD DADBIN |
| Drywall Nailing | 2/8/2024 | Approved | DARRYL ARNOLD |
| Wood Frame | 2/21/2024 | Partial Inspection | DARRYL ARNOLD |
| Insulation | 3/1/2024 | Approved | JACOB MYERS |
| Drywall Nailing | 3/8/2024 | Corrections Issued | DARRYL ARNOLD |
| Final | 8/6/2024 | OK for CofC | DARRYL ARNOLD |
| METHANE-Final | 8/6/2024 | Approved | DARRYL ARNOLD |
| Pre-Inspection | 10/14/2025 | Corrections Issued | DARRYL ARNOLD |
| Pre-Inspection | 12/18/2025 | Approved | DARRYL ARNOLD |