1550 S REEVES ST 90035

Certificate Information: 1550 S REEVES ST 90035

Application / Permit
22016-10000-13340
Plan Check / Job No.
B22LA08203
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlanLA: Interior and exterior remodel of 2 story SFD
Permit Issued
Issued on 10/20/2022
Issuing Office
Current Status
Permit Finaled on 3/6/2024

Permit Application Status History

Submitted 5/2/2022 APPLICANT
Assigned to Plan Check Engineer 5/3/2022 SUNMIN LEE
Corrections Issued 5/4/2022 SUNMIN LEE
Applicant returned to address corrections 7/25/2022 SUNMIN LEE
Applicant returned to address corrections 8/10/2022 SUNMIN LEE
Applicant returned to address corrections 8/23/2022 SUNMIN LEE
Applicant returned to address corrections 9/12/2022 SUNMIN LEE
Plan Check Approved 9/12/2022 SUNMIN LEE
No Progress 10/19/2022 SUNMIN LEE
Plan Check Approved 10/19/2022 SUNMIN LEE
Plan Check Approved 10/19/2022 JOHN FRANCIA
Issued 10/20/2022 APPLICANT
Permit Finaled 3/5/2024 OGANES TARAKHCHYAN

Permit Application Clearance Information

Grading Pre-Inspection Cleared 5/24/2022 ROBERT HUGHES
Eng Process Fee Ord 176,300 Cleared 5/26/2022 DINAH GARIN
Sewer availability Cleared 5/26/2022 DINAH GARIN

Contact Information

Contractor Owner-Builder       ,
Engineer Markarian,, Mardiros; Lic. No.: C53434 3814 VANALDEN AVE      TARZANA, CA 91356
Engineer Markarian,, Mardiros; Lic. No.: NA53434       ,

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/4/2022 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 11/14/2022 No Access for Inspection OGANES TARAKHCHYAN
Pre-Inspection 2/23/2023 Approved EVAN COOPER
Rough-Elec/Plmb/HVAC 3/10/2023 Partial Approval JEREMY TODD
ELECTRICAL-Rough 3/17/2023 Approved ASHLEY THOMPSON
HVAC-Rough 3/17/2023 Approved ASHLEY THOMPSON
PLUMBING-Rough 3/17/2023 Approved ASHLEY THOMPSON
Deputy Wood Construction 3/24/2023 Conditional Approval ASHLEY THOMPSON
BUILDING-Rough-Frame 4/3/2023 Conditional Approval ASHLEY THOMPSON
Final 4/3/2023 Corrections Issued ASHLEY THOMPSON
METHANE-Rough 4/3/2023 Approved ASHLEY THOMPSON
Insulation 4/6/2023 Approved MICHAEL PELHAM
Shower Pan 4/6/2023 Approved MICHAEL PELHAM
Drywall Nailing 4/19/2023 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 4/19/2023 Partial Approval ASHLEY THOMPSON
Interior/Exterior Lathing 5/5/2023 Approved ASHLEY THOMPSON
Gas Test 12/5/2023 Approved MEL KHACHATOURIAN
SGSOV-Seismic Gas S/O Valve 12/5/2023 SGSOV Approved MEL KHACHATOURIAN
ELECTRICAL-Final 1/11/2024 Corrections Issued JESUS PINEDA
HVAC-Final 1/11/2024 Approved JESUS PINEDA
Final 2/14/2024 Corrections Issued OGANES TARAKHCHYAN
BUILDING-Rough-Frame 2/29/2024 Approved OGANES TARAKHCHYAN
Smoke Detectors 2/29/2024 Approved OGANES TARAKHCHYAN
Final 3/5/2024 Permit Finaled OGANES TARAKHCHYAN