601 S FIGUEROA ST 90017

Certificate Information: 601 S FIGUEROA ST 90017

Application / Permit
22016-10000-13252
Plan Check / Job No.
B22LA08159
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
FULL FLOOR REMODEL OF FLOORS 16 AND 17. AREA OF WORK: 36,788 S.F
Permit Issued
Issued on 6/30/2022
Issuing Office
Current Status
Permit Finaled on 5/25/2023

Permit Application Status History

Submitted 4/29/2022 APPLICANT
Assigned to Plan Check Engineer 5/6/2022 LAWRENCE QUIRANTE
Corrections Issued 5/7/2022 LAWRENCE QUIRANTE
Building Plans Picked Up 5/11/2022 APPLICANT
Plan Check Approved 5/24/2022 KHUONG TRUONG
Issued 6/30/2022 APPLICANT
Permit Finaled 5/24/2023 KATY RAMIREZ

Permit Application Clearance Information

No Data Available.

Contact Information

Architect Wilder,, Arthur J; Lic. No.: C27915 3859 CARDIFF AVENUE      CULVER CITY, CA 90232
Contractor Corporate Contractors Inc; Lic. No.: 604407-B 2550 CORPORATE PL STE C-111      MONTEREY PARK, CA 91754

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 9/1/2022 Conditional Approval TIMOTHY BUXTON
Light Gage Steel Frame 9/22/2022 Approved TIMOTHY BUXTON
Drywall Nailing 10/3/2022 Partial Approval GREGORY POMISH
Drywall Nailing 10/6/2022 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 10/17/2022 Approved KATY RAMIREZ
T-Bar Ceiling 11/21/2022 Partial Inspection KATY RAMIREZ
Drywall Nailing 11/23/2022 Not Ready for Inspection ALAN MORELOS
T-Bar Ceiling 11/23/2022 Partial Inspection ALAN MORELOS
Final 5/24/2023 Permit Finaled KATY RAMIREZ
Green Building Final 5/24/2023 Approved KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 5/24/2023 SGSOV No Gas KATY RAMIREZ
Smoke Detectors 5/24/2023 Approved KATY RAMIREZ