1638 S GENESEE AVE 90019

Certificate Information: 1638 S GENESEE AVE 90019

Application / Permit
22016-10000-13240
Plan Check / Job No.
B22LA08146
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERTING AN (E) GARAGE AND STORAGE INTO AN ADU PER ENGR DESIGN
Permit Issued
Issued on 6/2/2022
Issuing Office
Metro
Current Status
CofO Issued on 7/1/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/29/2022 APPLICANT
Assigned to Plan Check Engineer 5/6/2022 JOSEPH RAFOLS
Corrections Issued 5/7/2022 JOSEPH RAFOLS
Building Plans Picked Up 5/13/2022 APPLICANT
Plan Check Approved 5/27/2022 MINA HABILI
Issued 6/2/2022 APPLICANT
CofO in Progress 6/27/2023 JOSE AVILA
Permit Finaled 7/1/2023 DEROLD HAUFF
Permit Finaled 7/1/2023 DEROLD HAUFF
CofO Issued 7/1/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/17/2022 JEANIE LAM
Sewer availability Cleared 5/17/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 5/18/2022 JEANIE LAM
Construction near power lines Cleared 5/26/2022 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/14/2022 Conditional Approval JOSE AVILA
Footing/Foundation/Slab 6/27/2022 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 8/16/2022 Corrections Issued JOSE AVILA
PLUMBING-Rough 10/27/2022 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 10/31/2022 Approved JOSE AVILA
PLUMBING-Rough 10/31/2022 Approved JOSE AVILA
Wood Frame 11/3/2022 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 11/8/2022 Partial Inspection JOSE AVILA
Green Building Rough 11/8/2022 Partial Inspection JOSE AVILA
METHANE-Rough 11/8/2022 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 11/17/2022 Approved JOSE AVILA
Wood Frame 11/17/2022 Off-Hour Fees Due
ELECTRICAL-Rough 11/30/2022 Corrections Issued JOSE AVILA
HVAC-Rough 11/30/2022 Corrections Issued JOSE AVILA
PLUMBING-Rough 11/30/2022 Partial Approval JOSE AVILA
BUILDING-Rough-Frame 12/9/2022 Approved JOSE AVILA
ELECTRICAL-Rough 12/9/2022 Approved JOSE AVILA
HVAC-Rough 12/9/2022 Approved JOSE AVILA
Drywall Nailing 12/13/2022 Approved MICHAEL LEWIS
Insulation 12/13/2022 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 2/13/2023 Approved JOSE AVILA
Green Building Rough 2/13/2023 Approved JOSE AVILA
Final 2/24/2023 Corrections Issued JOSE AVILA
Green Building Final 2/24/2023 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 2/24/2023 SGSOV Not Ready JOSE AVILA
Smoke Detectors 2/24/2023 Corrections Issued JOSE AVILA
ELECTRICAL-Final 3/3/2023 Approved JOSE AVILA
HVAC-Final 3/3/2023 Approved JOSE AVILA
PLUMBING-Final 3/3/2023 Approved JOSE AVILA
Final 4/4/2023 Not Ready for Inspection JOSE AVILA
SGSOV-Seismic Gas S/O Valve 4/4/2023 SGSOV Gas Company JOSE AVILA
Smoke Detectors 4/4/2023 Approved JOSE AVILA
Final 6/26/2023 OK to Issue CofO JOSE AVILA