6830 W DE LONGPRE AVE 90028
Certificate Information: 6830 W DE LONGPRE AVE 90028
- Application / Permit
- 22016-10000-13105
- Plan Check / Job No.
- B22LA08063
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL TO (E) 1-STORY SFD TO CREATE NEW BATH AND BEDROOM. INTERIOR NON-LOAD BEARING WALLS ADDED PER WFPP.
- Permit Issued
- Issued on 5/13/2022
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 6/17/2022
Permit Application Status History
| Submitted | 4/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/28/2022 | FERNANDO FLORES |
| Corrections Issued | 4/28/2022 | FERNANDO FLORES |
| Applicant returned to address corrections | 5/5/2022 | MINA HABILI |
| Plan Check Approved | 5/13/2022 | SHANGQIN XIE |
| Issued | 5/13/2022 | APPLICANT |
| Permit Finaled | 6/16/2022 | SHAVONNE ESPINOZA |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 5/4/2022 | MAX LODER |
| Redevelopment Project Area | Cleared | 5/10/2022 | GRACIELA ACOSTA |
Contact Information
| Contractor | Entheos Design Group Inc; Lic. No.: 940871-B | 5295 CAMERON DR #501 BUENA PARK, CA 90621 |
Inspector Information
| ROY SPAULDING, (213) 202-3461 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 6/1/2022 | Corrections Issued | RAUL BARAJAS |
| ELECTRICAL-Rough | 6/1/2022 | Approved | RAUL BARAJAS |
| PLUMBING-Rough | 6/1/2022 | Not Ready for Inspection | RAUL BARAJAS |
| BUILDING-Rough-Frame | 6/7/2022 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 6/7/2022 | Approved | RYAN SALAZAR |
| Drywall Nailing | 6/9/2022 | Conditional Approval | BRIAN SULLIVAN |
| Insulation | 6/9/2022 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Final | 6/15/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Final | 6/15/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Final | 6/15/2022 | Approved | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 6/15/2022 | SGSOV Not Ready | BRIAN SULLIVAN |
| Smoke Detectors | 6/15/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Final | 6/16/2022 | Permit Finaled | SHAVONNE ESPINOZA |
| SGSOV-Seismic Gas S/O Valve | 6/16/2022 | SGSOV Approved | SHAVONNE ESPINOZA |
| Smoke Detectors | 6/16/2022 | Approved | SHAVONNE ESPINOZA |