1462 S SHENANDOAH ST 90035

Certificate Information: 1462 S SHENANDOAH ST 90035

Application / Permit
22016-10000-13010
Plan Check / Job No.
B22LA08013
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
EPLAN: Soft-Story seismic retrofit per LABC Chapter 93: Verify work done under ADU conversion permit 22016-10000-12836 using (4) wood shear walls meets the minimum requirement of Soft Story Ordinance per LABC Chapter 93. **Certificate of Compliance for Soft Story will not be issued till Certificate of Occupancy for ADU permit is obtained**
Permit Issued
Issued on 6/20/2023
Issuing Office
Current Status
CofC Issued on 6/24/2025

Permit Application Status History

Submitted 4/28/2022 APPLICANT
Assigned to Plan Check Engineer 5/12/2022 HANS SANTIAGO
Corrections Issued 5/16/2022 HANS SANTIAGO
Quality Review Completed 5/19/2022 SAI KHUM
Plan Check Approved 8/19/2022 ANDREW SANTIAGO
Issued 6/20/2023 APPLICANT
OK for CofC 2/28/2025 DARRYL ARNOLD
CofC Issued 6/24/2025 ERNESTO CORRAL

Permit Application Clearance Information

Tenant Habitability Plan Cleared 6/14/2023 HUGO GARRIDO GARZA

Contact Information

Contractor Shaolian Sol K And Assoc Inc; Lic. No.: 720390-B       ,
Contractor Sks Construction; Lic. No.: 720390-B       ,
Engineer Alexander,, Andy; Lic. No.: C84086 1615 GRAMERCY AVE      TORRANCE, CA 90501

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/30/2023 Corrections Issued DARRYL ARNOLD
Footing/Foundation/Slab 11/28/2023 Conditional Approval DARRYL ARNOLD
Footing/Foundation/Slab 1/12/2024 No Access for Inspection DARRYL ARNOLD
Footing/Foundation/Slab 1/17/2024 Approved FARHAD DADBIN
Deputy Reinf. Concrete 1/18/2024 Conditional Approval DARRYL ARNOLD
Deputy Wood Construction 4/11/2024 Conditional Approval DARRYL ARNOLD
Wood Frame 4/16/2024 Approved DARRYL ARNOLD
Deputy Wood Construction 6/26/2024 Conditional Approval DARRYL ARNOLD
Wood Frame 7/16/2024 Conditional Approval DARRYL ARNOLD
Interior/Exterior Lathing 7/23/2024 Approved RONALD JIMENEZ
Final 12/16/2024 Not Ready for Inspection DARRYL ARNOLD
METHANE-Final 12/16/2024 Corrections Issued DARRYL ARNOLD
Final 2/28/2025 OK for CofC DARRYL ARNOLD
METHANE-Final 2/28/2025 Approved DARRYL ARNOLD