3010 N NORTH COOLIDGE AVE 90039
Certificate Information: 3010 N NORTH COOLIDGE AVE 90039
- Application / Permit
- 22016-10000-12911
- Plan Check / Job No.
- B22LA07931
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- TI: INTERIOR REMODEL TO CREATE NEW ATRIUM WITH CURTAIN WALL IN CENTER OF SPACE. NEW OFFICE AT MEZZANINE LEVEL. SEE COMMENT.
- Permit Issued
- Issued on 10/28/2022
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 2/7/2024
Permit Application Status History
| Submitted | 4/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/12/2022 | TSE MING HUANG |
| Corrections Issued | 5/17/2022 | TSE MING HUANG |
| Quality Review Completed | 5/24/2022 | KEN GILL |
| Building Plans Picked Up | 5/26/2022 | APPLICANT |
| Applicant returned to address corrections | 7/13/2022 | TSE MING HUANG |
| Applicant returned to address corrections | 7/29/2022 | TSE MING HUANG |
| Green Plans Picked Up | 8/1/2022 | APPLICANT |
| Plan Check Approved | 10/19/2022 | TSE MING HUANG |
| Issued | 10/28/2022 | APPLICANT |
| Permit Finaled | 2/6/2024 | RONALD JIMENEZ |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/24/2022 | JEANETTE VONG |
| Roof/Waste drainage to street | Cleared | 6/24/2022 | JEANETTE VONG |
| Green Code | Cleared | 6/27/2022 | DONALD CRICHLOW |
| "Q" conditions | Cleared | 7/12/2022 | JAZMIN ROQUE |
| CPC | Cleared | 7/12/2022 | JAZMIN ROQUE |
| ZI | Cleared | 7/12/2022 | JAZMIN ROQUE |
| DAS Clearance | Cleared | 8/24/2022 | TSE MING HUANG |
Contact Information
| Architect | Shubin,, Russell James; Lic. No.: C19250 | 3834 WILLAT AVENUE CULVER CITY, CA 90232 |
| Contractor | A & S Constructors Inc; Lic. No.: 921776-B | 937 MIRA VALLE ST MONTEREY PARK, CA 91754 |
| Engineer | Thorpe,, William Howard; Lic. No.: S3866 | 1649 PALAU PLACE COSTA MESA, CA 92626 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/9/2023 | Approved | RAFAEL CORTES |
| Wood Frame | 2/15/2023 | Partial Approval | JEROME BLACKWOOD |
| Pre-Inspection | 2/16/2023 | Corrections Issued | JEROME BLACKWOOD |
| Deputy Steel/Welding | 5/9/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Footing/Foundation/Slab | 7/3/2023 | Approved | JULIAN CAPUCETTI |
| Footing/Foundation/Slab | 7/25/2023 | Partial Approval | RAFAEL CORTES |
| Deputy Drilled-In Anchors | 8/11/2023 | Conditional Approval | RAFAEL CORTES |
| Footing/Foundation/Slab | 8/18/2023 | Partial Approval | RAFAEL CORTES |
| Light Gage Steel Frame | 9/28/2023 | Approved | RAFAEL CORTES |
| Insulation | 10/3/2023 | Approved | RAFAEL CORTES |
| Drywall Nailing | 10/10/2023 | Partial Approval | JACOB MYERS |
| Green Building Rough | 10/10/2023 | Partial Approval | JACOB MYERS |
| Drywall Nailing | 1/18/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Final | 1/18/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Green Building Final | 1/18/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Green Building Rough | 1/18/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Reinforced Concrete Frame | 1/18/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Reinforced Masonry Frame | 1/18/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| SGSOV-Seismic Gas S/O Valve | 1/18/2024 | SGSOV Not Ready | RAMAZANALI ALMASI |
| Smoke Detectors | 1/18/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Drywall Nailing | 2/6/2024 | Approved | RONALD JIMENEZ |
| Final | 2/6/2024 | Permit Finaled | RONALD JIMENEZ |
| Green Building Final | 2/6/2024 | Approved | RONALD JIMENEZ |
| Green Building Rough | 2/6/2024 | Approved | RONALD JIMENEZ |
| Reinforced Concrete Frame | 2/6/2024 | Approved | RONALD JIMENEZ |
| Reinforced Masonry Frame | 2/6/2024 | Approved | RONALD JIMENEZ |
| SGSOV-Seismic Gas S/O Valve | 2/6/2024 | SGSOV Approved | RONALD JIMENEZ |
| Smoke Detectors | 2/6/2024 | Approved | RONALD JIMENEZ |