3446 S COLONIAL AVE 90066

Certificate Information: 3446 S COLONIAL AVE 90066

Application / Permit
22016-10000-12835
Plan Check / Job No.
B22LA07886
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan Convert existing garage and storage into new 487 sf ADU per state law
Permit Issued
Issued on 7/13/2022
Issuing Office
Current Status
CofO Issued on 10/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/5/2022 APPLICANT
Assigned to Plan Check Engineer 5/12/2022 KHUONG TRUONG
Corrections Issued 5/13/2022 KHUONG TRUONG
Plan Check Approved 6/6/2022 KHUONG TRUONG
Issued 7/13/2022 APPLICANT
CofO in Progress 5/25/2023 JESUS RODRIGUEZ
No Progress 5/26/2023 JESUS RODRIGUEZ
CofO in Progress 10/3/2023 JESUS RODRIGUEZ
Permit Finaled 10/7/2023 DANIEL ORRANTE
CofO Issued 10/7/2023 DANIEL ORRANTE
Permit Finaled 10/7/2023 DANIEL ORRANTE

Permit Application Clearance Information

Sewer availability Cleared 5/26/2022 CATHERINE ADROVER
Address approval Cleared 6/1/2022 CATHERINE ADROVER
Eng Process Fee Ord 176,300 Cleared 6/1/2022 CATHERINE ADROVER
Roof/Waste drainage to street Cleared 6/1/2022 CATHERINE ADROVER
Grading Pre-Inspection Cleared 6/6/2022 KIRK LINKLATER

Contact Information

Contractor Benavides Builders Inc; Lic. No.: 1061451-B       ,
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/3/2022 Partial Approval JESUS RODRIGUEZ
PLUMBING-Rough 9/13/2022 Partial Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 9/16/2022 Not Ready for Inspection JESUS RODRIGUEZ
Footing/Foundation/Slab 9/20/2022 Corrections Issued JESUS RODRIGUEZ
Footing/Foundation/Slab 9/21/2022 Not Ready for Inspection HERBERT GIRON
Footing/Foundation/Slab 9/23/2022 Approved JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 10/25/2022 Conditional Approval HERBERT GIRON
ELECTRICAL-Rough 11/17/2022 Approved JESUS RODRIGUEZ
PLUMBING-Rough 11/17/2022 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 12/1/2022 Corrections Issued JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 12/1/2022 Corrections Issued JESUS RODRIGUEZ
HVAC-Rough 12/1/2022 Corrections Issued JESUS RODRIGUEZ
Insulation 12/1/2022 Corrections Issued JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 12/5/2022 Approved JESUS RODRIGUEZ
HVAC-Rough 12/5/2022 Approved JESUS RODRIGUEZ
Insulation 12/5/2022 Not Ready for Inspection JESUS RODRIGUEZ
BUILDING-Rough-Frame 12/6/2022 Approved JESUS RODRIGUEZ
Green Building Rough 12/6/2022 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 12/6/2022 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 12/12/2022 Approved JESUS RODRIGUEZ
Shower Pan 12/12/2022 Approved JESUS RODRIGUEZ
Sewer 12/23/2022 Approved JESUS RODRIGUEZ
Drywall Nailing 1/5/2023 Not Ready for Inspection JESUS RODRIGUEZ
Drywall Nailing 1/10/2023 Conditional Approval CLAYTON GRAHAM
Final 4/12/2023 Corrections Issued EVAN COOPER
ELECTRICAL-Final 5/24/2023 Approved JESUS RODRIGUEZ
Final 5/24/2023 OK to Issue CofO JESUS RODRIGUEZ
Green Building Final 5/24/2023 Approved JESUS RODRIGUEZ
HVAC-Final 5/24/2023 Approved JESUS RODRIGUEZ
PLUMBING-Final 5/24/2023 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 5/24/2023 SGSOV Approved JESUS RODRIGUEZ
Smoke Detectors 5/24/2023 Approved JESUS RODRIGUEZ
Final 5/26/2023 Corrections Issued JESUS RODRIGUEZ
Final 10/2/2023 OK to Issue CofO JESUS RODRIGUEZ