5738 N TYRONE AVE 91401

Certificate Information: 5738 N TYRONE AVE 91401

Application / Permit
22016-10000-12829
Plan Check / Job No.
B22LA07874
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL AND WINDOW CHANGE OUTS
Permit Issued
Issued on 5/24/2022
Issuing Office
Current Status
Permit Finaled on 6/23/2023

Permit Application Status History

Submitted 4/27/2022 APPLICANT
Assigned to Plan Check Engineer 5/3/2022 CARLOS MONTES
Plan Check Approved 5/4/2022 CARLOS MONTES
Issued 5/24/2022 APPLICANT
Permit Finaled 6/21/2023 RYAN SALAZAR

Permit Application Clearance Information

No Data Available.

Contact Information

Architect Moraga,, Ricky Garcia; Lic. No.: NA26008       ,
Contractor Owner-Builder       ,
Engineer Lobana,, Singh Maninder Pa; Lic. No.: C50989 885 PATRIOT DR #G      MOORPARK, CA 93021

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/12/2022 Corrections Issued RICHARD DOCKUS
Footing/Foundation/Slab 8/18/2022 Approved RICHARD DOCKUS
Excavation/Setback/Form/Re-Bar 9/6/2022 Approved RICHARD DOCKUS
Footing/Foundation/Slab 9/6/2022 Approved RICHARD DOCKUS
ELECTRICAL-Rough 10/26/2022 Approved RICHARD DOCKUS
PLUMBING-Rough 10/26/2022 Corrections Issued RICHARD DOCKUS
BUILDING-Rough-Frame 11/2/2022 Partial Approval RICHARD DOCKUS
HVAC-Rough 11/2/2022 Approved RICHARD DOCKUS
PLUMBING-Rough 11/2/2022 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 11/8/2022 Conditional Approval THOMAS FINNILA
Insulation 11/8/2022 Not Ready for Inspection THOMAS FINNILA
Insulation 11/15/2022 Partial Inspection ROBERT GOLD
Shower Pan 11/15/2022 Approved ROBERT GOLD
BUILDING-Rough-Frame 11/21/2022 Approved ROBERT GOLD
Insulation 11/21/2022 Approved ROBERT GOLD
Interior/Exterior Lathing 11/21/2022 Partial Approval ROBERT GOLD
Drywall Nailing 12/5/2022 Approved RYAN SALAZAR
Interior/Exterior Lathing 1/6/2023 Partial Approval RYAN SALAZAR
ELECTRICAL-Rough 3/21/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 3/21/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 5/4/2023 Approved RYAN SALAZAR
Final 6/21/2023 Permit Finaled RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 6/21/2023 SGSOV Approved RYAN SALAZAR
Smoke Detectors 6/21/2023 Approved RYAN SALAZAR