12121 W OLYMPIC BLVD 90064
Certificate Information: 12121 W OLYMPIC BLVD 90064
- Application / Permit
- 22016-10000-12625
- Plan Check / Job No.
- B22LA07708
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Grocery Store
- Work Description
- TENANT IMPROVEMENT ON FIRST FLOOR IN AN EXISTING 7-STORY MIXED-USE SHELL BUILDING, TYPE I-A CONSTRUCTION. ORIGINAL PERMIT PER 19010 - 10000 - 02627
- Permit Issued
- Issued on 10/12/2022
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 10/25/2023
Permit Application Status History
| Submitted | 4/27/2022 | APPLICANT |
| Green Plans Picked Up | 5/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/12/2022 | SERGIO GUTIERREZ |
| Corrections Issued | 5/26/2022 | SERGIO GUTIERREZ |
| Quality Review Completed | 6/1/2022 | KEN GILL |
| Building Plans Picked Up | 6/2/2022 | APPLICANT |
| Applicant returned to address corrections | 6/24/2022 | SERGIO GUTIERREZ |
| Plan Check Approved | 8/30/2022 | SERGIO GUTIERREZ |
| Issued | 10/12/2022 | APPLICANT |
| Permit Finaled | 10/25/2023 | FARHAD DADBIN |
Permit Application Clearance Information
| CPC | Cleared | 7/12/2022 | JAZMIN ROQUE |
| Miscellaneous | Cleared | 7/12/2022 | JAZMIN ROQUE |
| Green Code | Cleared | 7/14/2022 | KHEDER ALRAZAA |
| Fire Marshal Fire Life Safety | Cleared | 8/3/2022 | ANDREW KO |
| DAS Clearance | Cleared | 8/8/2022 | ELIZABETH TOMS |
| Food Service Establishment | Cleared | 8/8/2022 | KENNETH BROWNE |
| Food establishment approval | Cleared | 8/30/2022 | LACDHS APPROVED |
Contact Information
| Architect | Robich,, Paul Stanley; Lic. No.: C13724 | 6255 BLANCHARD CANYON RD TUJUNGA, CA 91042 |
| Contractor | Savant Construction Inc; Lic. No.: 596646-B | 13830 MOUNTAIN AVENUE CHINO, CA 91710 |
| Engineer | Baroonian,, Armen; Lic. No.: S4227 | 867 N FAIR OAKS AVE 100 PASADENA, CA 91103 |
Inspector Information
| CASIMIR BRITTON, (310) 914-3913 | Office Hours: 7:00-8:00 AM MON-FRI |
| SHAVONNE ESPINOZA, (310) 914-3913 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/22/2022 | Partial Approval | SORIN CIRSTOIU |
| Deputy Steel/Welding | 11/23/2022 | Conditional Approval | DAVID TSAU |
| Deputy Steel/Welding | 11/29/2022 | Conditional Approval | SORIN CIRSTOIU |
| Deputy Steel/Welding | 11/30/2022 | Conditional Approval | SORIN CIRSTOIU |
| Deputy Steel/Welding | 12/1/2022 | Approved | SORIN CIRSTOIU |
| Excavation/Setback/Form/Re-Bar | 12/1/2022 | Corrections Issued | SORIN CIRSTOIU |
| Footing/Foundation/Slab | 12/1/2022 | Partial Inspection | SORIN CIRSTOIU |
| Deputy Reinf. Concrete | 12/2/2022 | Approved | SORIN CIRSTOIU |
| Deputy Steel/Welding | 12/2/2022 | Approved | SORIN CIRSTOIU |
| Deputy Fireproofing | 12/8/2022 | Approved | SORIN CIRSTOIU |
| Deputy Reinf. Concrete | 12/8/2022 | Approved | SORIN CIRSTOIU |
| Deputy Steel/Welding | 12/8/2022 | Approved | SORIN CIRSTOIU |
| Excavation/Setback/Form/Re-Bar | 12/8/2022 | Partial Approval | SORIN CIRSTOIU |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2022 | Partial Approval | SORIN CIRSTOIU |
| Deputy Fireproofing | 12/9/2022 | Approved | SORIN CIRSTOIU |
| Deputy Reinf. Concrete | 12/9/2022 | Approved | SORIN CIRSTOIU |
| Deputy Steel/Welding | 12/9/2022 | Approved | SORIN CIRSTOIU |
| Excavation/Setback/Form/Re-Bar | 12/9/2022 | Partial Inspection | SORIN CIRSTOIU |
| Footing/Foundation/Slab | 12/9/2022 | Partial Inspection | SORIN CIRSTOIU |
| Reinforced Concrete Frame | 12/9/2022 | Partial Inspection | SORIN CIRSTOIU |
| Deputy Steel/Welding | 12/15/2022 | Conditional Approval | SORIN CIRSTOIU |
| Deputy Steel/Welding | 12/16/2022 | Approved | SORIN CIRSTOIU |
| Excavation/Setback/Form/Re-Bar | 12/16/2022 | Approved | SORIN CIRSTOIU |
| Deputy Reinf. Concrete | 12/19/2022 | Approved | SORIN CIRSTOIU |
| Light Gage Steel Frame | 1/17/2023 | Partial Approval | SORIN CIRSTOIU |
| Light Gage Steel Frame | 1/19/2023 | Conditional Approval | DERRICK SPENCER |
| Light Gage Steel Frame | 1/24/2023 | Partial Approval | DERRICK SPENCER |
| Light Gage Steel Frame | 2/1/2023 | Partial Approval | AMANUEL BERHE |
| Deputy Wood Construction | 2/9/2023 | Approved | DERRICK SPENCER |
| Light Gage Steel Frame | 2/9/2023 | Partial Approval | SORIN CIRSTOIU |
| Drywall Nailing | 2/16/2023 | Partial Approval | SORIN CIRSTOIU |
| Deputy Drilled-In Anchors | 4/26/2023 | Approved | SORIN CIRSTOIU |
| Deputy Steel/Welding | 4/27/2023 | Approved | SORIN CIRSTOIU |
| Light Gage Steel Frame | 5/9/2023 | Partial Approval | SORIN CIRSTOIU |
| T-Bar Ceiling | 7/12/2023 | Not Ready for Inspection | FARHAD DADBIN |
| T-Bar Ceiling | 7/18/2023 | Conditional Approval | FARHAD DADBIN |
| Special/Order Compliance | 9/13/2023 | Approved | DERRICK SPENCER |
| Special/Order Compliance | 9/25/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Special/Order Compliance | 9/29/2023 | Partial Approval | FARHAD DADBIN |
| Posting Pre-Inspection | 10/3/2023 | Partial Inspection | FARHAD DADBIN |
| Final | 10/17/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Green Building Final | 10/17/2023 | Approved | FARHAD DADBIN |
| Green Building Rough | 10/17/2023 | Approved | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 10/17/2023 | SGSOV Not Ready | FARHAD DADBIN |
| Smoke Detectors | 10/17/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Final | 10/20/2023 | Not Ready for Inspection | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 10/20/2023 | SGSOV Not Ready | FARHAD DADBIN |
| Smoke Detectors | 10/20/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Special/Order Compliance | 10/20/2023 | Not Ready for Inspection | FARHAD DADBIN |
| Special/Order Compliance | 10/24/2023 | Partial Inspection | FARHAD DADBIN |
| Final | 10/25/2023 | Permit Finaled | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 10/25/2023 | SGSOV Approved | FARHAD DADBIN |
| Smoke Detectors | 10/25/2023 | Approved | FARHAD DADBIN |
| Special/Order Compliance | 10/25/2023 | Approved | FARHAD DADBIN |