11960 W SUNSET BLVD 90049
Certificate Information: 11960 W SUNSET BLVD 90049
- Application / Permit
- 22016-10000-12547
- Plan Check / Job No.
- B22LA07618
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- PROPOSED SECURITY BOOTH
- Permit Issued
- Issued on 7/13/2023
- Issuing Office
- Current Status
- CofO Issued on 5/5/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/28/2022 | SINA KHOSRAVI |
| Corrections Issued | 5/4/2022 | SINA KHOSRAVI |
| Quality Review Completed | 5/9/2022 | CHARLES CHANG |
| Building Plans Picked Up | 5/12/2022 | APPLICANT |
| Applicant returned to address corrections | 11/8/2022 | SINA KHOSRAVI |
| Applicant returned to address corrections | 6/21/2023 | SINA KHOSRAVI |
| Plan Check Approved | 6/28/2023 | SINA KHOSRAVI |
| Issued | 7/13/2023 | APPLICANT |
| CofO in Progress | 5/4/2026 | DANIEL VARNUM |
| Permit Finaled | 5/5/2026 | VASIL MIHALEV |
| CofO Issued | 5/5/2026 | VASIL MIHALEV |
| Permit Finaled | 5/5/2026 | VASIL MIHALEV |
Permit Application Clearance Information
| ZA Case | Cleared | 5/25/2022 | DANIEL CORONADO |
| DAS Clearance | Cleared | 9/20/2022 | SINA KHOSRAVI |
| Miscellaneous | Cleared | 10/27/2022 | NOAH MCCOY |
| Green Code | Cleared | 6/15/2023 | AARON COSTA |
| Grading Pre-Inspection | Cleared | 7/13/2023 | SINA KHOSRAVI |
Contact Information
| Contractor | Jones & Jones Construction; Lic. No.: 917674-B | 1301 MARICOPA HIGHWAY OJAI, CA 93023 |
| Engineer | Cheyne,, Alex; Lic. No.: S4916 | 3212 NW SPARKS AVE ALBANY, OR 97321 |
Inspector Information
| CASIMIR BRITTON, (310) 914-3913 | Office Hours: 7:00-8:00 AM MON-FRI |
| SHAVONNE ESPINOZA, (310) 914-3913 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 2/20/2024 | Not Ready for Inspection | CASIMIR BRITTON |
| SGSOV-Seismic Gas S/O Valve | 2/20/2024 | SGSOV Not Ready | CASIMIR BRITTON |
| Smoke Detectors | 2/20/2024 | Not Ready for Inspection | CASIMIR BRITTON |
| Wood Frame | 2/20/2024 | Not Ready for Inspection | CASIMIR BRITTON |
| Final | 2/26/2024 | Not Ready for Inspection | CASIMIR BRITTON |
| SGSOV-Seismic Gas S/O Valve | 2/26/2024 | SGSOV Approved | CASIMIR BRITTON |
| Smoke Detectors | 2/26/2024 | Not Ready for Inspection | CASIMIR BRITTON |
| Wood Frame | 2/26/2024 | Approved | CASIMIR BRITTON |
| Final | 3/5/2024 | Conditional Approval | MICHAEL PETRUSKO |
| Smoke Detectors | 3/5/2024 | Approved | MICHAEL PETRUSKO |
| Special/Order Compliance | 5/4/2026 | Partial Inspection | DANIEL VARNUM |