4507 W PICO BLVD 90019
Certificate Information: 4507 W PICO BLVD 90019
- Application / Permit
- 22016-10000-12504
- Plan Check / Job No.
- B22LA07601
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Hair Dresser
- Work Description
- ePlan; CHANGE OF USE FROM (E) RETAIL TO (N) HAIR SALON
- Permit Issued
- Issued on 7/24/2023
- Issuing Office
- Current Status
- CofO Issued on 6/25/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/29/2022 | DANIEL YIP |
| Corrections Issued | 5/2/2022 | CARLOS MONTES |
| Applicant returned to address corrections | 7/27/2022 | DANIEL YIP |
| Applicant returned to address corrections | 9/9/2022 | DANIEL YIP |
| Plan Check Approved | 5/25/2023 | DANIEL YIP |
| Issued | 7/24/2023 | APPLICANT |
| CofO Issued | 6/25/2024 | ERNESTO CORRAL |
| Permit Finaled | 6/25/2024 | ERNESTO CORRAL |
Permit Application Clearance Information
| ZA Case | Cleared | 5/6/2022 | DALIA MOKAYED |
| ZA Case | Cleared | 5/6/2022 | DALIA MOKAYED |
| ZA Case | Cleared | 5/6/2022 | DALIA MOKAYED |
| ZA Case | Cleared | 5/6/2022 | DALIA MOKAYED |
| Historic Resource Verification | Cleared | 5/15/2023 | MAX LODER |
| Historic Resource Verification | Cleared | 5/18/2023 | YASMINE BASHIRI |
| Redevelopment Project Area | Cleared | 5/18/2023 | YASMINE BASHIRI |
| Redevelopment Project Area | Cleared | 5/18/2023 | YASMINE BASHIRI |
| Eng Process Fee Ord 176,300 | Cleared | 5/24/2023 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 5/24/2023 | ADRIAN SANCHEZ |
Contact Information
| Contractor | La Rocca Builders Inc; Lic. No.: 934161-B | , |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/15/2023 | Approved | ALFREDO LOPEZ |
| Final | 10/13/2023 | Partial Approval | ALFREDO LOPEZ |
| METHANE-Final | 10/13/2023 | Approved | ALFREDO LOPEZ |
| Final | 12/4/2023 | Not Ready for Inspection | ALFREDO LOPEZ |