11728 W GOSHEN AVE 90049
Certificate Information: 11728 W GOSHEN AVE 90049
- Application / Permit
- 22016-10000-12417
- Plan Check / Job No.
- B22LA07503
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan: Soft-Story seismic retrofit per LABC Chapter 93: By adding (1) 2 WAY SSCC at North - West and (1) 2 WAY SSCC at South - East elevation
- Permit Issued
- Issued on 10/4/2022
- Issuing Office
- Current Status
- CofC Issued on 4/18/2024
Permit Application Status History
| Submitted | 4/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/5/2022 | VARAND SARKISIAN |
| Corrections Issued | 5/12/2022 | VARAND SARKISIAN |
| Quality Review Completed | 5/16/2022 | HANS SANTIAGO |
| Plan Check Approved | 8/4/2022 | VARAND SARKISIAN |
| Issued | 10/4/2022 | APPLICANT |
| OK for CofC | 4/9/2024 | RICARDO ROBLES |
| CofC Issued | 4/18/2024 | HENRY BAGHDASSARIAN |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 10/4/2022 | MICHAEL SOTO |
Contact Information
| Contractor | Sks Construction; Lic. No.: 720390-B | 15134 FRIAR STREET VAN NUYS, CA 91411 |
| Engineer | Shaolian,, Shahab Joseph; Lic. No.: C84155 | 15134 FRIAR ST VAN NUYS, CA 91411 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/21/2022 | Approved | GRANT WOODS |
| Deputy Wood Construction | 1/11/2023 | Conditional Approval | SHAVONNE ESPINOZA |
| Deputy Steel/Welding | 2/10/2023 | Approved | AMANUEL BERHE |
| Deputy Drilled-In Anchors | 2/16/2023 | Conditional Approval | ALAN NOVAK |
| Footing/Foundation/Slab | 2/22/2023 | Approved | ALAN NOVAK |
| Structural Steel Frame | 2/22/2023 | Approved | ALAN NOVAK |
| Wood Frame | 2/22/2023 | Approved | ALAN NOVAK |
| Deputy Reinf. Concrete | 2/23/2023 | Conditional Approval | ALAN NOVAK |
| Interior/Exterior Lathing | 3/8/2023 | Approved | ALAN NOVAK |
| Final | 9/11/2023 | Not Ready for Inspection | MICHAEL PETRUSKO |
| SGSOV-Seismic Gas S/O Valve | 9/11/2023 | SGSOV Not Ready | MICHAEL PETRUSKO |
| Smoke Detectors | 9/11/2023 | Not Ready for Inspection | MICHAEL PETRUSKO |
| Final | 9/13/2023 | Corrections Issued | MICHAEL PETRUSKO |
| SGSOV-Seismic Gas S/O Valve | 9/13/2023 | SGSOV Not Ready | MICHAEL PETRUSKO |
| Smoke Detectors | 9/13/2023 | Not Ready for Inspection | MICHAEL PETRUSKO |
| Final | 4/3/2024 | Not Ready for Inspection | RICARDO ROBLES |
| SGSOV-Seismic Gas S/O Valve | 4/3/2024 | SGSOV Not Ready | RICARDO ROBLES |
| Smoke Detectors | 4/3/2024 | Approved | RICARDO ROBLES |
| Final | 4/5/2024 | Not Ready for Inspection | RICARDO ROBLES |
| Final | 4/9/2024 | OK for CofC | RICARDO ROBLES |
| SGSOV-Seismic Gas S/O Valve | 4/9/2024 | SGSOV Approved | RICARDO ROBLES |