7294 N FIGUEROA ST 90041
Certificate Information: 7294 N FIGUEROA ST 90041
- Application / Permit
- 22016-10000-12408
- Plan Check / Job No.
- B22LA07498
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ADU PER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 11/1/2022
- Issuing Office
- Current Status
- CofO Issued on 8/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/6/2022 | ZAW HAN |
| Corrections Issued | 5/10/2022 | ZAW HAN |
| Building Plans Picked Up | 5/16/2022 | APPLICANT |
| Applicant returned to address corrections | 6/9/2022 | RACHEL BEYENE |
| Applicant returned to address corrections | 6/23/2022 | MINA HABILI |
| Plan Check Approved | 9/16/2022 | LUKE GONZALES |
| Issued | 11/1/2022 | APPLICANT |
| CofO in Progress | 6/27/2023 | BRIAN SULLIVAN |
| Permit Finaled | 8/7/2023 | RONALD MYRICK |
| CofO Issued | 8/7/2023 | RONALD MYRICK |
| Permit Finaled | 8/7/2023 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 5/24/2022 | STEVE MELGAR |
| Roof/Waste drainage to street | Cleared | 5/24/2022 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 5/25/2022 | STEVE MELGAR |
| Grading Pre-Inspection | Cleared | 5/25/2022 | KIRK LINKLATER |
| Sewer availability | Cleared | 5/25/2022 | STEVE MELGAR |
Contact Information
| Contractor | Akr Construction Inc; Lic. No.: 1065837-B | 12729 RIVERSIDE DR #301 VALLEY VILLAGE, CA 91607 |
| Engineer | Kaballo,, Amir; Lic. No.: C90707 | 152 S SWALL DR BEVERLY HILLS, CA 90211 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/1/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Underground Mechanical | 12/1/2022 | Partial Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 12/15/2022 | Corrections Issued | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 12/21/2022 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 1/30/2023 | Partial Approval | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 1/30/2023 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Rough | 1/30/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 1/30/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 1/30/2023 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 2/2/2023 | Approved | JEFFREY MEAD |
| HVAC-Rough | 2/2/2023 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 2/2/2023 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 2/6/2023 | Partial Approval | SCOTT FINNILA |
| Green Building Rough | 2/6/2023 | Partial Approval | SCOTT FINNILA |
| Interior/Exterior Lathing | 2/6/2023 | Partial Approval | SCOTT FINNILA |
| Insulation | 2/9/2023 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 2/9/2023 | Partial Approval | CRAIG VAUGHAN |
| Drywall Nailing | 2/13/2023 | Approved | CRAIG VAUGHAN |
| Shower Pan | 2/13/2023 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 2/15/2023 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 3/29/2023 | Approved | ALIZAH MAYAGOITIA |
| Final | 3/29/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 3/29/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Rough | 3/29/2023 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 3/29/2023 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 3/29/2023 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 3/29/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Smoke Detectors | 3/29/2023 | Approved | ALIZAH MAYAGOITIA |
| Final | 4/3/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| Green Building Final | 4/3/2023 | Approved | BRIAN SULLIVAN |
| Service/Power Release | 4/3/2023 | Approved | BRIAN SULLIVAN |
| Final | 6/26/2023 | OK to Issue CofO | BRIAN SULLIVAN |