8909 S HALLDALE AVE 90047
Certificate Information: 8909 S HALLDALE AVE 90047
- Application / Permit
- 22016-10000-12368
- Plan Check / Job No.
- B22LA07460
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: CONVERT (E) GARAGE TO (N) 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 5/18/2022
- Issuing Office
- Current Status
- CofO Issued on 2/19/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/26/2022 | DANIEL YIP |
| Corrections Issued | 4/27/2022 | DANIEL YIP |
| Plan Check Approved | 5/15/2022 | DANIEL YIP |
| Issued | 5/18/2022 | APPLICANT |
| CofO in Progress | 9/22/2022 | HORACE FULTZ |
| Permit Finaled | 2/19/2023 | DEROLD HAUFF |
| CofO Issued | 2/19/2023 | DEROLD HAUFF |
| Permit Finaled | 2/19/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/10/2022 | ABEL CASILLAS |
| Sewer availability | Cleared | 5/10/2022 | ABEL CASILLAS |
| Eng Process Fee Ord 176,300 | Cleared | 5/11/2022 | ABEL CASILLAS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 7/12/2022 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 7/12/2022 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 7/18/2022 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 8/3/2022 | Corrections Issued | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 8/3/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| HVAC-Rough | 8/3/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 8/3/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 8/5/2022 | Corrections Issued | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 8/5/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| HVAC-Rough | 8/5/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 8/5/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 8/10/2022 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 8/10/2022 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 8/10/2022 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 8/10/2022 | Approved | ENRIQUE MIRELES |
| Insulation | 8/18/2022 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 8/18/2022 | Approved | ENRIQUE MIRELES |
| Sewer | 8/18/2022 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 8/22/2022 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 9/6/2022 | SGSOV Not Ready | ENRIQUE MIRELES |
| ELECTRICAL-Final | 9/15/2022 | Approved | ENRIQUE MIRELES |
| Final | 9/15/2022 | Corrections Issued | ENRIQUE MIRELES |
| HVAC-Final | 9/15/2022 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 9/15/2022 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 9/15/2022 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 9/15/2022 | Approved | ENRIQUE MIRELES |
| Final | 9/20/2022 | OK to Issue CofO | ENRIQUE MIRELES |
| Service/Power Release | 9/20/2022 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 9/21/2022 | Approved | ENRIQUE MIRELES |
| HVAC-Final | 9/21/2022 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 9/21/2022 | Approved | ENRIQUE MIRELES |