1811 1/4 W 24TH ST 90018

Certificate Information: 1811 1/4 W 24TH ST 90018

Application / Permit
22016-10000-12301
Plan Check / Job No.
B22LA07389
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) .
Permit Issued
Issued on 10/28/2022
Issuing Office
Metro
Current Status
CofO Issued on 2/13/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/22/2022 APPLICANT
Assigned to Plan Check Engineer 4/25/2022 RACHEL BEYENE
Corrections Issued 4/27/2022 RACHEL BEYENE
Building Plans Picked Up 5/2/2022 APPLICANT
Applicant returned to address corrections 10/24/2022 MINA HABILI
Plan Check Approved 10/28/2022 GEORGE ALVAREZ
Issued 10/28/2022 APPLICANT
CofO in Progress 2/12/2024 ARTHUR NEGRETE
CofO Issued 2/13/2024 DEROLD HAUFF
Permit Finaled 2/13/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/1/2022 CINDY QI
Sewer availability Cleared 9/1/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 9/7/2022 CINDY QI
Community Plan Implem. Overlay Cleared 10/12/2022 RAFAEL FONTES

Contact Information

Contractor Owner-Builder       ,
Engineer Finley,, Lawrence Rufus; Lic. No.: C46606 1178 E 9TH ST      LONG BEACH, CA 90813

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/27/2023 Approved KATHRYN BUTTERWORTH
Footing/Foundation/Slab 2/27/2023 Approved KATHRYN BUTTERWORTH
Deputy Wood Construction 3/29/2023 Conditional Approval KATHRYN BUTTERWORTH
ELECTRICAL-Rough 4/3/2023 Corrections Issued SCOTT FINNILA
PLUMBING-Rough 4/3/2023 Approved SCOTT FINNILA
Sewer 4/3/2023 Approved SCOTT FINNILA
Wood Frame 4/3/2023 Partial Approval SCOTT FINNILA
BUILDING-Rough-Frame 5/5/2023 Corrections Issued KATHRYN BUTTERWORTH
Green Building Rough 5/5/2023 Approved KATHRYN BUTTERWORTH
MERV13>=Rough 5/5/2023 Approved KATHRYN BUTTERWORTH
METHANE-Rough 5/5/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
Wood Frame 5/5/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 5/19/2023 Approved STUART CHAPMAN
ELECTRICAL-Rough 5/19/2023 Approved STUART CHAPMAN
Interior/Exterior Lathing 5/19/2023 Partial Approval STUART CHAPMAN
METHANE-Rough 5/19/2023 Approved STUART CHAPMAN
Wood Frame 5/19/2023 Not Ready for Inspection STUART CHAPMAN
Insulation 5/30/2023 Approved JEFFREY MEAD
Drywall Nailing 6/15/2023 Approved KATHRYN BUTTERWORTH
Final 9/1/2023 Corrections Issued KATHRYN BUTTERWORTH
Green Building Final 9/1/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
MERV13>=Final 9/1/2023 Approved KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 9/1/2023 SGSOV Not Ready KATHRYN BUTTERWORTH
Smoke Detectors 9/1/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
Final 10/23/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
Green Building Final 10/23/2023 Approved KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 10/23/2023 SGSOV Approved KATHRYN BUTTERWORTH
Smoke Detectors 10/23/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
ELECTRICAL-Final 2/9/2024 Approved ARTHUR NEGRETE
Final 2/9/2024 OK to Issue CofO ARTHUR NEGRETE
HVAC-Final 2/9/2024 Approved ARTHUR NEGRETE
PLUMBING-Final 2/9/2024 Approved ARTHUR NEGRETE
Smoke Detectors 2/9/2024 Approved ARTHUR NEGRETE