5877 W FRANKLIN AVE 90028
Certificate Information: 5877 W FRANKLIN AVE 90028
- Application / Permit
- 22016-10000-12258
- Plan Check / Job No.
- B22LA07351
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- ePlan : GROCERY MARKET TENANT INTERIOR RENOVATION & EXTERIOR UNENCLOSED PATIO AREA OF WORK - 1,600 SF
- Permit Issued
- Issued on 11/10/2022
- Issuing Office
- Current Status
- Permit Finaled on 3/15/2023
Permit Application Status History
| Submitted | 5/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/25/2022 | RAHEL BEYENE |
| Corrections Issued | 5/25/2022 | RAHEL BEYENE |
| Disabled Access Plans Picked Up | 5/26/2022 | APPLICANT |
| Applicant returned to address corrections | 6/10/2022 | RAHEL BEYENE |
| Applicant returned to address corrections | 8/22/2022 | RAHEL BEYENE |
| Applicant returned to address corrections | 10/16/2022 | RAHEL BEYENE |
| Plan Check Approved | 11/3/2022 | RAHEL BEYENE |
| Issued | 11/10/2022 | APPLICANT |
| Permit Finaled | 3/14/2023 | MARTIN TAVITIAN |
Permit Application Clearance Information
| ZA Case | Cleared | 6/28/2022 | DANIEL CORONADO |
| ZA Case | Cleared | 6/28/2022 | DANIEL CORONADO |
| ZA Case | Cleared | 6/28/2022 | DANIEL CORONADO |
| DAS Clearance | Cleared | 10/14/2022 | Hernan Arreola |
| Food establishment approval | Cleared | 11/3/2022 | LACDHS APPROVED |
Contact Information
| Architect | Kelley,, Kevin E; Lic. No.: NA27298 | , |
| Contractor | B S M Construction Inc; Lic. No.: 828014-B | , |
| Engineer | Baroonian,, Armen; Lic. No.: S4227 | 867 N FAIR OAKS AVE 100 PASADENA, CA 91103 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/15/2022 | Approved | DAVID BURKHEAD |
| Light Gage Steel Frame | 1/4/2023 | Corrections Issued | RONALD JIMENEZ |
| Light Gage Steel Frame | 1/9/2023 | Not Ready for Inspection | GREGORY POMISH |
| Deputy Reinf. Masonry | 1/10/2023 | No Access for Inspection | RONALD JIMENEZ |
| Masonry Wall/Backfill | 1/12/2023 | Corrections Issued | TIMOTHY POWELL |
| Deputy Reinf. Masonry | 1/17/2023 | Conditional Approval | RONALD JIMENEZ |
| Light Gage Steel Frame | 1/17/2023 | Partial Approval | RONALD JIMENEZ |
| Masonry Wall/Backfill | 1/18/2023 | Partial Approval | RONALD JIMENEZ |
| Drywall Nailing | 1/20/2023 | Partial Approval | RAMAZANALI ALMASI |
| Masonry Wall/Backfill | 1/24/2023 | Partial Approval | ALFREDO LOPEZ |
| Deputy Reinf. Masonry | 1/25/2023 | Conditional Approval | TIMOTHY POWELL |
| Excavation/Setback/Form/Re-Bar | 1/26/2023 | Corrections Issued | TIMOTHY POWELL |
| Masonry Wall/Backfill | 1/26/2023 | Not Ready for Inspection | TIMOTHY POWELL |
| Deputy Reinf. Masonry | 1/27/2023 | No Access for Inspection | TIMOTHY POWELL |
| Light Gage Steel Frame | 1/27/2023 | Corrections Issued | TIMOTHY POWELL |
| Excavation/Setback/Form/Re-Bar | 1/30/2023 | Partial Approval | TIMOTHY POWELL |
| Drywall Nailing | 2/2/2023 | Partial Approval | RONALD JIMENEZ |
| Excavation/Setback/Form/Re-Bar | 2/2/2023 | Partial Approval | RONALD JIMENEZ |
| Structural Steel Frame | 2/2/2023 | Partial Approval | RONALD JIMENEZ |
| Excavation/Setback/Form/Re-Bar | 2/3/2023 | Approved | MARTIN TAVITIAN |
| Light Gage Steel Frame | 2/8/2023 | Partial Approval | TIMOTHY POWELL |
| Masonry Wall/Backfill | 2/8/2023 | Partial Approval | TIMOTHY POWELL |
| Drywall Nailing | 2/14/2023 | Approved | RONALD JIMENEZ |
| Final | 3/10/2023 | Conditional Approval | MARTIN TAVITIAN |
| SGSOV-Seismic Gas S/O Valve | 3/10/2023 | SGSOV Approved | MARTIN TAVITIAN |
| Smoke Detectors | 3/10/2023 | Approved | MARTIN TAVITIAN |
| Final | 3/14/2023 | Permit Finaled | MARTIN TAVITIAN |