7731 N AMESTOY AVE 91406
Certificate Information: 7731 N AMESTOY AVE 91406
- Application / Permit
- 22016-10000-12149
- Plan Check / Job No.
- B22LA07250
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EXTERIOR AND INTERIOR REMODEL OF EXISTING 1 STORY SINGLE FAMILY DEWLLING (NO CHANGE IN FLOOR AREA OR HEIGHT)
- Permit Issued
- Issued on 5/25/2022
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 8/2/2022
Permit Application Status History
| Submitted | 4/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/25/2022 | ZAW HAN |
| Corrections Issued | 4/25/2022 | ZAW HAN |
| Building Plans Picked Up | 4/26/2022 | APPLICANT |
| Plan Check Approved | 5/18/2022 | AUNG SOE |
| Issued | 5/25/2022 | APPLICANT |
| Permit Finaled | 8/1/2022 | RAUL OLAGI |
Permit Application Clearance Information
| Sewer availability | Cleared | 4/26/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/2/2022 | MEGAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Martirossyan,, Armen; Lic. No.: C64223 | 802 PORTOLA AVE GLENDALE, CA 91206 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 6/1/2022 | Not Ready for Inspection | DEANDRE HOFFMAN |
| ELECTRICAL-Rough | 6/1/2022 | Corrections Issued | DEANDRE HOFFMAN |
| HVAC-Rough | 6/1/2022 | Corrections Issued | DEANDRE HOFFMAN |
| PLUMBING-Rough | 6/1/2022 | Corrections Issued | DEANDRE HOFFMAN |
| Wood Frame | 6/1/2022 | Corrections Issued | DEANDRE HOFFMAN |
| BUILDING-Rough-Frame | 6/7/2022 | Not Ready for Inspection | ALAN MORELOS |
| Interior/Exterior Lathing | 6/7/2022 | Partial Approval | ALAN MORELOS |
| Rough-Elec/Plmb/HVAC | 6/7/2022 | Corrections Issued | ALAN MORELOS |
| ELECTRICAL-Rough | 6/10/2022 | Approved | ALAN MORELOS |
| PLUMBING-Rough | 6/10/2022 | Approved | ALAN MORELOS |
| Wood Frame | 6/10/2022 | Corrections Issued | ALAN MORELOS |
| BUILDING-Rough-Frame | 6/20/2022 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 6/20/2022 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 6/20/2022 | Conditional Approval | CARLOS MATAMOROS |
| Shower Pan | 6/20/2022 | Approved | CARLOS MATAMOROS |
| Insulation | 6/27/2022 | Approved | ALAN MORELOS |
| Drywall Nailing | 7/1/2022 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 7/1/2022 | Approved | ALAN MORELOS |
| ELECTRICAL-Final | 8/1/2022 | Approved | RAUL OLAGI |
| Final | 8/1/2022 | Permit Finaled | RAUL OLAGI |
| Green Building Final | 8/1/2022 | Approved | RAUL OLAGI |
| HVAC-Final | 8/1/2022 | Approved | RAUL OLAGI |
| PLUMBING-Final | 8/1/2022 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 8/1/2022 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 8/1/2022 | Approved | RAUL OLAGI |