4015 W MARATHON ST 90029
Certificate Information: 4015 W MARATHON ST 90029
- Application / Permit
- 22016-10000-12072
- Plan Check / Job No.
- B22LA07194
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LAMC DIV. 93 USING CANTILEVER COLUMNS
- Permit Issued
- Issued on 9/15/2023
- Issuing Office
- Metro
- Current Status
- CofC Issued on 10/10/2025
Permit Application Status History
| Submitted | 4/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/28/2022 | JESSE VIDUYA |
| Corrections Issued | 5/9/2022 | JESSE VIDUYA |
| Quality Review Completed | 5/9/2022 | HANS SANTIAGO |
| Plan Check Approved | 4/4/2023 | JESSE VIDUYA |
| Issued | 9/15/2023 | APPLICANT |
| OK for CofC | 10/6/2025 | DARRYL ARNOLD |
| CofC Issued | 10/10/2025 | ERNESTO CORRAL |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 8/23/2023 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Intrepid Builders Inc; Lic. No.: 1063638-B | 1420 NORTH SIERRA BONITA #408 LOS ANGELES, CA 90046 |
| Engineer | Moeini,, Soheil; Lic. No.: C84000 | 11022 SANTA MONICA BLVD STE 440 LOS ANGELES, CA 90025 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/27/2023 | Approved | VAHE KELEDJIAN |
| Deputy Drilled-In Anchors | 10/13/2023 | Conditional Approval | VAHE KELEDJIAN |
| Deputy Reinf. Concrete | 10/13/2023 | Conditional Approval | VAHE KELEDJIAN |
| Deputy Steel/Welding | 10/13/2023 | Conditional Approval | VAHE KELEDJIAN |
| Footing/Foundation/Slab | 10/30/2023 | Partial Approval | JACOB MYERS |
| Wood Frame | 10/30/2023 | Partial Approval | JACOB MYERS |
| Deputy Reinf. Concrete | 10/31/2023 | Partial Approval | JACOB MYERS |
| Interior/Exterior Lathing | 11/3/2023 | Approved | JACOB MYERS |
| Final | 12/27/2023 | Not Ready for Inspection | JACOB MYERS |
| SGSOV-Seismic Gas S/O Valve | 12/27/2023 | SGSOV Not Ready | JACOB MYERS |
| Smoke Detectors | 12/27/2023 | Approved | JACOB MYERS |
| Final | 8/12/2025 | Conditional Approval | RONALD JIMENEZ |
| SGSOV-Seismic Gas S/O Valve | 8/12/2025 | SGSOV Approved | RONALD JIMENEZ |
| Final | 10/6/2025 | OK for CofC | DARRYL ARNOLD |