31 E WASHINGTON BLVD 90292
Certificate Information: 31 E WASHINGTON BLVD 90292
- Application / Permit
- 22016-10000-12043
- Plan Check / Job No.
- B22LA07158
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant - Take Out
- Work Description
- T.I. for (E) take out restaurant with new beverage station, (N) accessible restrooms and partitions. (E) outdoor dinnig to remain, (N) facade remodel and small addittion for the restrooms and bar and reinforcement of roof for new mechanical equipment.
- Permit Issued
- Issued on 9/29/2023
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 9/5/2025
Permit Application Status History
| Submitted | 4/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/5/2022 | SALVADOR QUINTANILLA |
| Corrections Issued | 5/16/2022 | SALVADOR QUINTANILLA |
| Quality Review Completed | 5/17/2022 | KEN GILL |
| Disabled Access Plans Picked Up | 5/17/2022 | APPLICANT |
| Green Plans Picked Up | 6/30/2022 | APPLICANT |
| Applicant returned to address corrections | 6/8/2023 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 6/9/2023 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 8/9/2023 | SALVADOR QUINTANILLA |
| Plan Check Approved | 8/16/2023 | SALVADOR QUINTANILLA |
| Issued | 9/29/2023 | APPLICANT |
| Permit Finaled | 9/8/2025 | FARHAD DADBIN |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/26/2022 | TREVOR QUAN |
| Sewer availability | Cleared | 5/26/2022 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 5/31/2022 | TREVOR QUAN |
| Specific Plan | Cleared | 6/1/2022 | FREDDY GARCIA |
| Green Code | Cleared | 8/2/2022 | AARON COSTA |
| Highway dedication | Cleared | 2/24/2023 | AHMED AMARRAGY |
| DAS Clearance | Cleared | 3/8/2023 | SALVADOR QUINTANILLA |
| Specific Plan | Cleared | 7/24/2023 | IRA BROWN |
| Food Service Establishment | Cleared | 7/27/2023 | PAWAN VERMA |
| Demolition Pre-Inspection | Cleared | 8/14/2023 | SALVADOR QUINTANILLA |
| Food establishment approval | Cleared | 8/14/2023 | LACDHS APPROVED |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Alexander,, Andy; Lic. No.: C84086 | 1615 GRAMERCY AVE TORRANCE, CA 90501 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/26/2023 | Conditional Approval | FARHAD DADBIN |
| Excavation/Setback/Form/Re-Bar | 10/27/2023 | Partial Approval | FARHAD DADBIN |
| Deputy Reinf. Concrete | 5/8/2024 | Conditional Approval | PAUL DAVIDSON |
| Footing/Foundation/Slab | 5/8/2024 | Not Ready for Inspection | FARHAD DADBIN |
| METHANE-Barrier | 5/8/2024 | Partial Approval | FARHAD DADBIN |
| METHANE-Subgrade | 5/8/2024 | Partial Approval | FARHAD DADBIN |
| Footing/Foundation/Slab | 6/12/2024 | Not Ready for Inspection | FARHAD DADBIN |
| METHANE-Barrier | 6/12/2024 | Partial Approval | FARHAD DADBIN |
| METHANE-Subgrade | 6/12/2024 | Partial Approval | FARHAD DADBIN |
| Excavation/Setback/Form/Re-Bar | 6/13/2024 | Corrections Issued | FARHAD DADBIN |
| Footing/Foundation/Slab | 6/18/2024 | Approved | FARHAD DADBIN |
| METHANE-Barrier | 6/18/2024 | Approved | FARHAD DADBIN |
| METHANE-Subgrade | 6/18/2024 | Approved | FARHAD DADBIN |
| Floor/Roof Diaphrgm/Shear Wall | 7/3/2024 | Not Ready for Inspection | FARHAD DADBIN |
| Floor/Roof Diaphrgm/Shear Wall | 7/5/2024 | Partial Approval | FARHAD DADBIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2024 | Not Ready for Inspection | FARHAD DADBIN |
| Green Building Rough | 8/26/2024 | Approved | FARHAD DADBIN |
| METHANE-Rough | 8/26/2024 | Approved | FARHAD DADBIN |
| Wood Frame | 8/26/2024 | Not Ready for Inspection | FARHAD DADBIN |
| Deputy Wood Construction | 9/12/2024 | Conditional Approval | FARHAD DADBIN |
| Floor/Roof Diaphrgm/Shear Wall | 10/10/2024 | Corrections Issued | FARHAD DADBIN |
| Wood Frame | 10/10/2024 | Conditional Approval | FARHAD DADBIN |
| Insulation | 12/20/2024 | Partial Approval | FARHAD DADBIN |
| Drywall Nailing | 12/31/2024 | Approved | FARHAD DADBIN |
| T-Bar Ceiling | 2/21/2025 | Not Ready for Inspection | FARHAD DADBIN |
| Interior/Exterior Lathing | 3/7/2025 | Conditional Approval | FARHAD DADBIN |
| Final | 6/17/2025 | Not Ready for Inspection | FARHAD DADBIN |
| Green Building Final | 6/17/2025 | Approved | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 6/17/2025 | SGSOV Approved | FARHAD DADBIN |
| Smoke Detectors | 6/17/2025 | Approved | FARHAD DADBIN |
| Wood Frame | 6/17/2025 | Approved | FARHAD DADBIN |
| Final | 9/8/2025 | Permit Finaled | FARHAD DADBIN |