1118 W 37TH DR 90007
Certificate Information: 1118 W 37TH DR 90007
- Application / Permit
- 22016-10000-11848
- Plan Check / Job No.
- B22LA07007
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Remodeling of (E) 2 Story, Type VB, 5-Unit apartment building to create an additional bedroom in each unit; infill of exterior wall openings.
- Permit Issued
- Issued on 6/21/2022
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 8/15/2022
Permit Application Status History
| Submitted | 4/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/5/2022 | KESETE HAREGOT |
| Corrections Issued | 5/13/2022 | KESETE HAREGOT |
| Disabled Access Plans Picked Up | 5/13/2022 | APPLICANT |
| Quality Review Completed | 5/16/2022 | RODOLFO ARIAS |
| Building Plans Picked Up | 5/20/2022 | APPLICANT |
| Plan Check Approved | 6/21/2022 | KESETE HAREGOT |
| Issued | 6/21/2022 | APPLICANT |
| Permit Finaled | 8/12/2022 | RUSSELL BONVOULOIR |
Permit Application Clearance Information
| "D" conditions | Cleared | 5/25/2022 | RAFAEL FONTES |
| Community Plan Implem. Overlay | Cleared | 5/25/2022 | RAFAEL FONTES |
| DAS Clearance | Cleared | 6/7/2022 | KESETE HAREGOT |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hwang,, Junho; Lic. No.: S5592 | 815 FAIRVIEW AVE #205 SOUTH PASADENA, CA 91030 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/23/2022 | Partial Approval | NICK DANERI |
| Interior/Exterior Lathing | 7/8/2022 | Approved | RUSSELL BONVOULOIR |
| Wood Frame | 7/8/2022 | Partial Inspection | RUSSELL BONVOULOIR |
| Drywall Nailing | 7/12/2022 | Approved | RUSSELL BONVOULOIR |
| Insulation | 7/12/2022 | Approved | RUSSELL BONVOULOIR |
| Drywall Nailing | 7/20/2022 | Approved | RUSSELL BONVOULOIR |
| Insulation | 7/20/2022 | Approved | RUSSELL BONVOULOIR |
| Final | 8/12/2022 | Permit Finaled | RUSSELL BONVOULOIR |
| SGSOV-Seismic Gas S/O Valve | 8/12/2022 | SGSOV Approved | RUSSELL BONVOULOIR |
| Smoke Detectors | 8/12/2022 | Approved | RUSSELL BONVOULOIR |