12044 W CLOVER AVE 90066
Certificate Information: 12044 W CLOVER AVE 90066
- Application / Permit
- 22016-10000-11781
- Plan Check / Job No.
- B22LA06944
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan 397 SF DETTACHED GARAGE CONVERSION TO ADU. Plancheck per GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 6/12/2022
- Issuing Office
- Current Status
- CofO Issued on 12/30/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/22/2022 | SUNMIN LEE |
| Corrections Issued | 4/25/2022 | SUNMIN LEE |
| Applicant returned to address corrections | 5/26/2022 | SUNMIN LEE |
| Plan Check Approved | 6/1/2022 | SUNMIN LEE |
| Issued | 6/12/2022 | APPLICANT |
| CofO in Progress | 6/22/2023 | JOHNNY MIRANDA |
| Permit Finaled | 12/30/2023 | DANIEL ORRANTE |
| CofO Issued | 12/30/2023 | DANIEL ORRANTE |
| Permit Finaled | 12/30/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 5/4/2022 | JENSON LEE |
| Roof/Waste drainage to street | Cleared | 5/4/2022 | JENSON LEE |
| Sewer availability | Cleared | 5/4/2022 | JENSON LEE |
| Grading Pre-Inspection | Cleared | 5/10/2022 | KIRK LINKLATER |
| Construction within easement | Cleared | 5/23/2022 | WALTER RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/26/2022 | JENSON LEE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | He,, Zizhao; Lic. No.: NA6930 | , |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/2/2022 | Partial Approval | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 12/20/2022 | Conditional Approval | RICHARD STEINBACH |
| PLUMBING-Rough | 1/23/2023 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 1/26/2023 | Approved | RICHARD STEINBACH |
| PLUMBING-Rough | 1/26/2023 | Partial Approval | RICHARD STEINBACH |
| Underground Mechanical | 1/26/2023 | Partial Approval | RICHARD STEINBACH |
| BUILDING-Rough-Frame | 2/24/2023 | Partial Approval | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 2/24/2023 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 2/24/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| HVAC-Rough | 2/24/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| PLUMBING-Rough | 2/24/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| Rough-Elec/Plmb/HVAC | 2/24/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| Shower Pan | 2/24/2023 | Approved | JOHNNY MIRANDA |
| Underground Mechanical | 2/24/2023 | Partial Approval | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 3/3/2023 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2023 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 3/3/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| HVAC-Rough | 3/3/2023 | Approved | JOHNNY MIRANDA |
| PLUMBING-Rough | 3/3/2023 | Approved | JOHNNY MIRANDA |
| Insulation | 3/9/2023 | Corrections Issued | DAVID FEILER |
| Interior/Exterior Lathing | 3/9/2023 | Not Ready for Inspection | DAVID FEILER |
| BUILDING-Rough-Frame | 3/13/2023 | Approved | EVAN COOPER |
| Green Building Rough | 3/13/2023 | Approved | EVAN COOPER |
| Insulation | 3/13/2023 | Corrections Issued | EVAN COOPER |
| Interior/Exterior Lathing | 3/13/2023 | Partial Approval | EVAN COOPER |
| Insulation | 3/14/2023 | Approved | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 3/22/2023 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 3/22/2023 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 3/28/2023 | Approved | JOHNNY MIRANDA |
| Sewer | 5/11/2023 | Approved | JOHNNY MIRANDA |
| Final | 6/12/2023 | Corrections Issued | JOHNNY MIRANDA |
| Green Building Final | 6/12/2023 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 6/12/2023 | SGSOV Approved | JOHNNY MIRANDA |
| Smoke Detectors | 6/12/2023 | Approved | JOHNNY MIRANDA |
| Final | 6/20/2023 | OK to Issue CofO | JOHNNY MIRANDA |