12044 W CLOVER AVE 90066

Certificate Information: 12044 W CLOVER AVE 90066

Application / Permit
22016-10000-11781
Plan Check / Job No.
B22LA06944
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan 397 SF DETTACHED GARAGE CONVERSION TO ADU. Plancheck per GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 6/12/2022
Issuing Office
Current Status
CofO Issued on 12/30/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/19/2022 APPLICANT
Assigned to Plan Check Engineer 4/22/2022 SUNMIN LEE
Corrections Issued 4/25/2022 SUNMIN LEE
Applicant returned to address corrections 5/26/2022 SUNMIN LEE
Plan Check Approved 6/1/2022 SUNMIN LEE
Issued 6/12/2022 APPLICANT
CofO in Progress 6/22/2023 JOHNNY MIRANDA
Permit Finaled 12/30/2023 DANIEL ORRANTE
CofO Issued 12/30/2023 DANIEL ORRANTE
Permit Finaled 12/30/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 5/4/2022 JENSON LEE
Roof/Waste drainage to street Cleared 5/4/2022 JENSON LEE
Sewer availability Cleared 5/4/2022 JENSON LEE
Grading Pre-Inspection Cleared 5/10/2022 KIRK LINKLATER
Construction within easement Cleared 5/23/2022 WALTER RAMIREZ
Eng Process Fee Ord 176,300 Cleared 5/26/2022 JENSON LEE

Contact Information

Contractor Owner-Builder       ,
Engineer He,, Zizhao; Lic. No.: NA6930       ,

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/2/2022 Partial Approval JOHNNY MIRANDA
Footing/Foundation/Slab 12/20/2022 Conditional Approval RICHARD STEINBACH
PLUMBING-Rough 1/23/2023 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 1/26/2023 Approved RICHARD STEINBACH
PLUMBING-Rough 1/26/2023 Partial Approval RICHARD STEINBACH
Underground Mechanical 1/26/2023 Partial Approval RICHARD STEINBACH
BUILDING-Rough-Frame 2/24/2023 Partial Approval JOHNNY MIRANDA
ELECTRICAL-Rough 2/24/2023 Approved JOHNNY MIRANDA
Green Building Rough 2/24/2023 Not Ready for Inspection JOHNNY MIRANDA
HVAC-Rough 2/24/2023 Not Ready for Inspection JOHNNY MIRANDA
PLUMBING-Rough 2/24/2023 Not Ready for Inspection JOHNNY MIRANDA
Rough-Elec/Plmb/HVAC 2/24/2023 Not Ready for Inspection JOHNNY MIRANDA
Shower Pan 2/24/2023 Approved JOHNNY MIRANDA
Underground Mechanical 2/24/2023 Partial Approval JOHNNY MIRANDA
BUILDING-Rough-Frame 3/3/2023 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 3/3/2023 Approved JOHNNY MIRANDA
Green Building Rough 3/3/2023 Not Ready for Inspection JOHNNY MIRANDA
HVAC-Rough 3/3/2023 Approved JOHNNY MIRANDA
PLUMBING-Rough 3/3/2023 Approved JOHNNY MIRANDA
Insulation 3/9/2023 Corrections Issued DAVID FEILER
Interior/Exterior Lathing 3/9/2023 Not Ready for Inspection DAVID FEILER
BUILDING-Rough-Frame 3/13/2023 Approved EVAN COOPER
Green Building Rough 3/13/2023 Approved EVAN COOPER
Insulation 3/13/2023 Corrections Issued EVAN COOPER
Interior/Exterior Lathing 3/13/2023 Partial Approval EVAN COOPER
Insulation 3/14/2023 Approved CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 3/22/2023 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 3/22/2023 Approved JOHNNY MIRANDA
Drywall Nailing 3/28/2023 Approved JOHNNY MIRANDA
Sewer 5/11/2023 Approved JOHNNY MIRANDA
Final 6/12/2023 Corrections Issued JOHNNY MIRANDA
Green Building Final 6/12/2023 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 6/12/2023 SGSOV Approved JOHNNY MIRANDA
Smoke Detectors 6/12/2023 Approved JOHNNY MIRANDA
Final 6/20/2023 OK to Issue CofO JOHNNY MIRANDA