620 E 249TH ST 90744
Certificate Information: 620 E 249TH ST 90744
- Application / Permit
- 22016-10000-11711
- Plan Check / Job No.
- B22LA06891
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- ePLAN. NEW DETACHED TRASH ENCLOSURE.
- Permit Issued
- Issued on 5/16/2022
- Issuing Office
- Current Status
- CofO Issued on 3/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/21/2022 | KEVIN MORALES |
| Corrections Issued | 4/21/2022 | KEVIN MORALES |
| Applicant returned to address corrections | 5/5/2022 | KEVIN MORALES |
| Plan Check Approved | 5/13/2022 | KEVIN MORALES |
| Issued | 5/16/2022 | APPLICANT |
| CofO in Progress | 3/22/2023 | JOEY BUCHANAN |
| Permit Finaled | 3/29/2023 | DAVID TSAU |
| CofO Issued | 3/29/2023 | DAVID TSAU |
| Permit Finaled | 3/29/2023 | DAVID TSAU |
Permit Application Clearance Information
| Miscellaneous | Cleared | 5/5/2022 | NOAH MCCOY |
| Eng Process Fee Ord 176,300 | Cleared | 5/6/2022 | JOSE HERNANDEZ |
| Roof/Waste drainage to street | Cleared | 5/6/2022 | JOSE HERNANDEZ |
Contact Information
| Architect | Palmer,, Keith Stanton; Lic. No.: C11096 | 715 BAY HILL DRIVE NEWPORT BEACH, CA 92660 |
| Contractor | Del Amo Construction Llc; Lic. No.: 744458-B | , |
| Engineer | Labib,, Youhanna T.; Lic. No.: S4549 | 319 MAIN STREET EL SEGUNDO, CA 90245 |
Inspector Information
| MICHAEL PETRUSKO, (310) 732-4552 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Interior/Exterior Lathing | 7/25/2022 | Approved | JOEY BUCHANAN |
| Final | 8/18/2022 | Conditional Approval | JOEY BUCHANAN |
| Footing/Foundation/Slab | 8/18/2022 | Approved | JOEY BUCHANAN |
| METHANE-Barrier | 8/18/2022 | Approved | JOEY BUCHANAN |
| METHANE-Final | 8/18/2022 | Approved | JOEY BUCHANAN |
| METHANE-Rough | 8/18/2022 | Approved | JOEY BUCHANAN |
| METHANE-Subgrade | 8/18/2022 | Approved | JOEY BUCHANAN |
| Reinforced Concrete Frame | 8/18/2022 | Approved | JOEY BUCHANAN |
| SGSOV-Seismic Gas S/O Valve | 8/18/2022 | SGSOV Approved | JOEY BUCHANAN |
| Smoke Detectors | 8/18/2022 | Approved | JOEY BUCHANAN |
| Verify Sprinkler Sign Off | 8/18/2022 | Approved | JOEY BUCHANAN |