533 1/2 W COLDEN AVE 90044

Certificate Information: 533 1/2 W COLDEN AVE 90044

Application / Permit
22016-10000-11659
Plan Check / Job No.
B22LA06867
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONSTRUCT 1 DETACHED ADU AND REMOVE GARAGE ATTACHED TO EXISTING MULTI FAMILY DWELLING
Permit Issued
Issued on 1/20/2023
Issuing Office
Current Status
CofO Corrected on 8/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/25/2022 APPLICANT
Assigned to Plan Check Engineer 6/24/2022 MARCELA FRANQUEZ
Corrections Issued 6/30/2022 MARCELA FRANQUEZ
Quality Review Completed 7/8/2022 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 11/16/2022 MARCELA FRANQUEZ
Applicant returned to address corrections 12/20/2022 MARCELA FRANQUEZ
Plan Check Approved 1/6/2023 MARCELA FRANQUEZ
Issued 1/20/2023 APPLICANT
CofO in Progress 1/8/2024 JOHN KLARIN
Re-Activate Permit 8/22/2024 ANSON MAGLASANG
CofO Issued-Status Void 8/22/2024 ANSON MAGLASANG
Permit Finaled-Status Void 8/22/2024 ANSON MAGLASANG
Permit Finaled 8/22/2024 ANSON MAGLASANG
CofO Corrected 8/22/2024 ANSON MAGLASANG
Permit Finaled 8/22/2024 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 8/8/2022 JEANIE LAM
Sewer availability Cleared 8/8/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 8/12/2022 JEANIE LAM
Tenant Habitability Plan Cleared 11/16/2022 ISMAEL HERNANDEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/17/2023 Not Ready for Inspection JAMES CHAVEZ
Special/Order Compliance 3/17/2023 Not Ready for Inspection JAMES CHAVEZ
Excavation/Setback/Form/Re-Bar 3/20/2023 Corrections Issued JAMES CHAVEZ
Footing/Foundation/Slab 3/22/2023 Approved JAMES CHAVEZ
Footing/Foundation/Slab 3/28/2023 Approved JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 4/18/2023 Partial Approval JAMES CHAVEZ
Green Building Rough 4/18/2023 Not Ready for Inspection JAMES CHAVEZ
Verify Sprinkler Sign Off 4/18/2023 Not Ready for Inspection JAMES CHAVEZ
Deputy Drilled-In Anchors 4/20/2023 Conditional Approval JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 4/20/2023 Approved JAMES CHAVEZ
Interior/Exterior Lathing 5/5/2023 Not Ready for Inspection JAMES CHAVEZ
Insulation 6/29/2023 Corrections Issued JAMES CHAVEZ
Drywall Nailing 7/3/2023 Not Ready for Inspection JAMES CHAVEZ
Green Building Rough 7/3/2023 Not Ready for Inspection JAMES CHAVEZ
Drywall Nailing 7/13/2023 Approved JAMES CHAVEZ
Green Building Rough 7/13/2023 Approved JAMES CHAVEZ
Interior/Exterior Lathing 7/13/2023 Approved JAMES CHAVEZ
Final 8/14/2023 Not Ready for Inspection JOHN KLARIN
Green Building Final 8/14/2023 Not Ready for Inspection JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 8/14/2023 SGSOV Not Ready JOHN KLARIN
Smoke Detectors 8/14/2023 Not Ready for Inspection JOHN KLARIN
Verify Sprinkler Sign Off 8/14/2023 Not Ready for Inspection JOHN KLARIN
Wood Frame 8/14/2023 Corrections Issued JOHN KLARIN
Final 12/7/2023 Corrections Issued JOHN KLARIN
Green Building Final 12/7/2023 Corrections Issued JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 12/7/2023 SGSOV Not Ready JOHN KLARIN
Smoke Detectors 12/7/2023 Approved JOHN KLARIN
Verify Sprinkler Sign Off 12/7/2023 Approved JOHN KLARIN
Wood Frame 12/7/2023 Not Ready for Inspection JOHN KLARIN
Final 12/13/2023 Corrections Issued JOHN KLARIN
Green Building Final 12/13/2023 Not Ready for Inspection JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 12/13/2023 SGSOV Not Required JOHN KLARIN
Wood Frame 12/13/2023 Partial Approval JOHN KLARIN
Pre-Inspection 12/19/2023 Corrections Issued JOHN KLARIN
Final 1/5/2024 OK to Issue CofO JOHN KLARIN
Green Building Final 1/5/2024 Approved JOHN KLARIN
Wood Frame 1/5/2024 Approved JOHN KLARIN