2242 S PATRICIA AVE 90064
Certificate Information: 2242 S PATRICIA AVE 90064
- Application / Permit
- 22016-10000-11510
- Plan Check / Job No.
- B22LA06720
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan CONVERT EXISTING GARAGE TO ACCESSORY DWELLING UNIT PER ORDINANCE.
- Permit Issued
- Issued on 1/23/2023
- Issuing Office
- Current Status
- CofO Issued on 1/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/18/2022 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 4/18/2022 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 5/6/2022 | FARSHAD ALIMOHAMADI |
| Issued | 1/23/2023 | APPLICANT |
| Permit Expired-Status Void | 3/9/2024 | MICHAEL PELHAM |
| Re-Activate Permit | 4/10/2024 | MICHAEL PELHAM |
| CofO in Progress | 1/15/2025 | STEPHANIE SWANSON |
| CofO Issued | 1/15/2025 | RICHARD STEINBACH |
| Permit Finaled | 1/15/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 4/21/2022 | NIKTA MOUSAVI |
| Sewer availability | Cleared | 4/21/2022 | NIKTA MOUSAVI |
| Eng Process Fee Ord 176,300 | Cleared | 4/22/2022 | NIKTA MOUSAVI |
| Specific Plan | Cleared | 4/27/2022 | EDUARDO HERMOSO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 3/9/2024 | Not Ready for Inspection | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 4/16/2024 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 4/16/2024 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 4/16/2024 | Conditional Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 4/16/2024 | Corrections Issued | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 5/20/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| METHANE-Rough | 5/20/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| Rough-Elec/Plmb/HVAC | 5/20/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 5/29/2024 | Partial Approval | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 5/29/2024 | Approved | STEPHANIE SWANSON |
| HVAC-Rough | 5/29/2024 | Approved | STEPHANIE SWANSON |
| PLUMBING-Rough | 5/29/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| PLUMBING-Rough | 5/31/2024 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 6/11/2024 | Approved | STEPHANIE SWANSON |
| Insulation | 6/11/2024 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 6/11/2024 | Partial Approval | STEPHANIE SWANSON |
| Drywall Nailing | 6/20/2024 | Approved | CHRISTOPHER WILSON |
| Shower Pan | 6/20/2024 | Approved | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 6/25/2024 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 12/9/2024 | Corrections Issued | STEPHANIE SWANSON |
| Final | 12/9/2024 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Final | 12/9/2024 | Approved | STEPHANIE SWANSON |
| PLUMBING-Final | 12/9/2024 | Approved | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 12/9/2024 | SGSOV Approved | STEPHANIE SWANSON |
| Smoke Detectors | 12/9/2024 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 12/23/2024 | Approved | STEPHANIE SWANSON |
| Final | 12/23/2024 | Corrections Issued | STEPHANIE SWANSON |
| Final | 1/15/2025 | OK to Issue CofO | STEPHANIE SWANSON |
| Service/Power Release | 1/15/2025 | Approved | STEPHANIE SWANSON |