12203 W LOUISE AVE 90066
Certificate Information: 12203 W LOUISE AVE 90066
- Application / Permit
- 22016-10000-11480
- Plan Check / Job No.
- B22LA06701
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 640 SF INTERIOR RESIDENTIAL REMODEL WITH REPLACEMENT OF SELECT WINDOWS IN EXISTING OPENINGS. NO ADDITION TO EXISTING AREAS
- Permit Issued
- Issued on 2/13/2023
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 1/25/2024
Permit Application Status History
| Submitted | 4/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/27/2022 | ADAM HEGAZI |
| Corrections Issued | 4/28/2022 | ADAM HEGAZI |
| Building Plans Picked Up | 5/5/2022 | APPLICANT |
| Plan Check Approved | 5/26/2022 | KHUONG TRUONG |
| Issued | 2/13/2023 | APPLICANT |
| Permit Finaled | 1/24/2024 | JESUS RODRIGUEZ |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Chan,, John K; Lic. No.: C35342 | 722 PARKMAN AVENUE LOS ANGELES, CA 90026 |
| Contractor | Build Zone Corp; Lic. No.: 1098273-B | , |
| Engineer | Garza,, Omar Leonel; Lic. No.: S5593 | 600 WILSHIRE BLVD 760 LOS ANGELES, CA 90017 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/23/2023 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 3/1/2023 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/7/2023 | Partial Approval | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 6/26/2023 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 6/26/2023 | Approved | JESUS RODRIGUEZ |
| Insulation | 7/3/2023 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 7/3/2023 | Partial Approval | JESUS RODRIGUEZ |
| Drywall Nailing | 7/10/2023 | Partial Approval | JESUS RODRIGUEZ |
| Shower Pan | 7/19/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Wood Frame | 7/19/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 8/11/2023 | Approved | JESUS PINEDA |
| Shower Pan | 8/11/2023 | Partial Approval | JESUS PINEDA |
| Shower Pan | 8/15/2023 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 9/5/2023 | Corrections Issued | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 1/24/2024 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 1/24/2024 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 1/24/2024 | Approved | JESUS RODRIGUEZ |
| Final | 1/24/2024 | Permit Finaled | JESUS RODRIGUEZ |
| HVAC-Final | 1/24/2024 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 1/24/2024 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 1/24/2024 | SGSOV Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 1/24/2024 | Approved | JESUS RODRIGUEZ |