839 N PARKMAN AVE 90026
Certificate Information: 839 N PARKMAN AVE 90026
- Application / Permit
- 22016-10000-11455
- Plan Check / Job No.
- B22LA06676
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- ePlan Convert 2 (E) Underfloor Spaces to (N) Storage Spaces.
- Permit Issued
- Issued on 3/9/2023
- Issuing Office
- Current Status
- CofO Issued on 3/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/18/2022 | HANS SANTIAGO |
| Corrections Issued | 4/19/2022 | HANS SANTIAGO |
| Applicant returned to address corrections | 11/9/2022 | HANS SANTIAGO |
| Plan Check Approved | 1/25/2023 | ANDREW SANTIAGO |
| Issued | 3/9/2023 | APPLICANT |
| CofO in Progress | 2/18/2025 | LUIS CCAMACHO |
| Permit Finaled | 3/3/2025 | ERNESTO CORRAL |
| CofO Issued | 3/3/2025 | ERNESTO CORRAL |
| Permit Finaled | 3/3/2025 | ERNESTO CORRAL |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 12/27/2022 | ROBERT HUGHES |
| GPI Written Notices | Cleared | 1/25/2023 | ANDREW SANTIAGO |
Contact Information
| Architect | Kellen,, David; Lic. No.: C15684 | 2701 AIRPORT AVE 202 SANTA MONICA, CA 90405 |
| Contractor | Owner-Builder | , |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/8/2023 | Conditional Approval | RONALD JIMENEZ |
| Deputy Drilled-In Anchors | 8/9/2023 | Approved | TIMOTHY POWELL |
| Footing/Foundation/Slab | 1/11/2024 | Approved | JACOB MYERS |
| Insulation | 1/22/2024 | Approved | JEROME BLACKWOOD |
| METHANE-Rough | 1/22/2024 | Not Ready for Inspection | JEROME BLACKWOOD |
| Wood Frame | 1/22/2024 | Not Ready for Inspection | JEROME BLACKWOOD |
| Reinforced Masonry Frame | 2/2/2024 | Partial Approval | LUIS CCAMACHO |
| Excavation/Setback/Form/Re-Bar | 9/23/2024 | Partial Approval | LUIS CCAMACHO |
| Floor/Roof Diaphrgm/Shear Wall | 11/19/2024 | Partial Approval | LUIS CCAMACHO |
| Drywall Nailing | 11/27/2024 | Partial Approval | CHRISTOPHER BLACKWOOD |
| Interior/Exterior Lathing | 11/27/2024 | Partial Approval | CHRISTOPHER BLACKWOOD |
| Drywall Nailing | 12/2/2024 | Partial Approval | LUIS CCAMACHO |
| Drywall Nailing | 2/12/2025 | Approved | LUIS CCAMACHO |
| Final | 2/12/2025 | Not Ready for Inspection | LUIS CCAMACHO |
| Green Building Final | 2/12/2025 | Approved | LUIS CCAMACHO |
| METHANE-Final | 2/12/2025 | Approved | LUIS CCAMACHO |
| METHANE-Rough | 2/12/2025 | Approved | LUIS CCAMACHO |
| SGSOV-Seismic Gas S/O Valve | 2/12/2025 | SGSOV Approved | LUIS CCAMACHO |
| Smoke Detectors | 2/12/2025 | Approved | LUIS CCAMACHO |
| Wood Frame | 2/12/2025 | Approved | LUIS CCAMACHO |
| Final | 2/18/2025 | OK to Issue CofO | LUIS CCAMACHO |