845 W 56TH ST 90037

Certificate Information: 845 W 56TH ST 90037

Application / Permit
22016-10000-11390
Plan Check / Job No.
B22LA06646
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
FULL INTERIOR REMODEL OF (E) SFD 1 OF 2
Permit Issued
Issued on 12/21/2022
Issuing Office
Current Status
Permit Finaled on 7/9/2024

Permit Application Status History

Submitted 4/13/2022 APPLICANT
Assigned to Plan Check Engineer 4/28/2022 ADRIANA LOPEZ
Corrections Issued 5/11/2022 ADRIANA LOPEZ
Quality Review Completed 5/13/2022 FARUK SEZER
Building Plans Picked Up 5/18/2022 APPLICANT
Applicant returned to address corrections 11/23/2022 ADRIANA LOPEZ
Plan Check Approved 12/21/2022 ADRIANA LOPEZ
Issued 12/21/2022 APPLICANT
Permit Finaled 7/8/2024 CRAIG DAVIS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/22/2022 CELINA MORENO
Sewer availability Cleared 8/22/2022 CELINA MORENO
Tenant Habitability Plan Cleared 8/25/2022 MICHAEL SOTO

Contact Information

Contractor Owner-Builder       ,
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Rough-Elec/Plmb/HVAC 9/1/2023 Approved SABAS ALONSO
BUILDING-Rough-Frame 10/30/2023 Not Ready for Inspection CRAIG DAVIS
Pre-Inspection 10/30/2023 Not Ready for Inspection CRAIG DAVIS
Footing/Foundation/Slab 3/12/2024 Corrections Issued DAVID FEILER
BUILDING-Rough-Frame 3/15/2024 Not Ready for Inspection CRAIG DAVIS
Footing/Foundation/Slab 3/15/2024 Partial Approval CRAIG DAVIS
BUILDING-Rough-Frame 3/22/2024 Partial Inspection CRAIG DAVIS
Wood Frame 3/22/2024 Partial Inspection CRAIG DAVIS
ELECTRICAL-Rough 4/10/2024 Approved JOSE MACIAS
HVAC-Rough 4/10/2024 Approved JOSE MACIAS
PLUMBING-Rough 4/10/2024 Approved JOSE MACIAS
BUILDING-Rough-Frame 4/11/2024 Approved JOSE MACIAS
Insulation 4/12/2024 Corrections Issued CRAIG DAVIS
Drywall Nailing 4/16/2024 Not Ready for Inspection CRAIG DAVIS
Interior/Exterior Lathing 4/16/2024 Corrections Issued CRAIG DAVIS
Drywall Nailing 4/18/2024 Approved CRAIG DAVIS
Pre-Inspection 4/18/2024 Partial Inspection CRAIG DAVIS
Gas Test 5/3/2024 Not Ready for Inspection CRAIG DAVIS
ELECTRICAL-Final 6/5/2024 Corrections Issued CRAIG DAVIS
HVAC-Final 6/5/2024 Corrections Issued CRAIG DAVIS
PLUMBING-Final 6/5/2024 Corrections Issued CRAIG DAVIS
ELECTRICAL-Final 7/1/2024 Corrections Issued CRAIG DAVIS
Final 7/1/2024 Not Ready for Inspection CRAIG DAVIS
HVAC-Final 7/1/2024 Corrections Issued CRAIG DAVIS
MERV13>=Final 7/1/2024 Corrections Issued CRAIG DAVIS
PLUMBING-Final 7/1/2024 Not Ready for Inspection CRAIG DAVIS
SGSOV-Seismic Gas S/O Valve 7/1/2024 SGSOV Not Ready CRAIG DAVIS
Smoke Detectors 7/1/2024 Approved CRAIG DAVIS
Final 7/8/2024 Permit Finaled CRAIG DAVIS
SGSOV-Seismic Gas S/O Valve 7/8/2024 SGSOV Approved CRAIG DAVIS