870 N ILIFF ST 90272

Certificate Information: 870 N ILIFF ST 90272

Application / Permit
22016-10000-11319
Plan Check / Job No.
B22LA06602
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
KITCHEN REMODEL TO EXISTING 1-STORY SFD WITH NEW EXTERIOR DECK. Add beams, foundation elements, and shearwalls per engineer.
Permit Issued
Issued on 6/3/2022
Issuing Office
Metro
Current Status
Permit Finaled on 2/2/2023

Permit Application Status History

Submitted 4/12/2022 APPLICANT
Assigned to Plan Check Engineer 4/26/2022 JESSE JIMENEZ
Corrections Issued 4/27/2022 JESSE JIMENEZ
Building Plans Picked Up 4/29/2022 APPLICANT
Plan Check Approved 5/12/2022 GEORGE ALVAREZ
Issued 6/3/2022 APPLICANT
Permit Finaled 2/1/2023 OGANES TARAKHCHYAN

Permit Application Clearance Information

Grading Pre-Inspection Cleared 5/12/2022 JESSE JIMENEZ

Contact Information

Contractor Pni Construction Inc; Lic. No.: 970399-B 1505 KINGHAM WAY      FULLERTON, CA 92833
Engineer Chung,, Keith Hoon; Lic. No.: C40602 15220 TRICIA LANE      LA MIRADA, CA 90638

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/28/2022 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 7/29/2022 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Rough 8/15/2022 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 8/15/2022 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Rough 8/23/2022 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 8/23/2022 Corrections Issued KEVIN SARGSYAN
Wood Frame 8/23/2022 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Rough 9/6/2022 Approved KEVIN SARGSYAN
PLUMBING-Rough 9/6/2022 Not Ready for Inspection KEVIN SARGSYAN
Wood Frame 9/6/2022 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 9/13/2022 Corrections Issued KEVIN SARGSYAN
Insulation 9/13/2022 Partial Approval KEVIN SARGSYAN
PLUMBING-Rough 9/13/2022 Corrections Issued KEVIN SARGSYAN
BUILDING-Rough-Frame 9/16/2022 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 9/16/2022 Approved KEVIN SARGSYAN
Insulation 9/16/2022 Approved KEVIN SARGSYAN
PLUMBING-Rough 9/16/2022 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 9/19/2022 Partial Approval KEVIN SARGSYAN
Drywall Nailing 9/21/2022 Approved KEVIN SARGSYAN
Shower Pan 9/21/2022 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 9/30/2022 Approved KEVIN SARGSYAN
Final 11/30/2022 Corrections Issued KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 11/30/2022 SGSOV Not Ready KEVIN SARGSYAN
Smoke Detectors 11/30/2022 Corrections Issued KEVIN SARGSYAN
Final 1/26/2023 Corrections Issued OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 1/26/2023 SGSOV Not Ready OGANES TARAKHCHYAN
Smoke Detectors 1/26/2023 Approved OGANES TARAKHCHYAN
Final 2/1/2023 Permit Finaled OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 2/1/2023 SGSOV Approved OGANES TARAKHCHYAN